[COM] Goodwood Junction Rail Underpass | $110m

Threads relating to transport, water, etc. within the CBD and Metropolitan area.
Message
Author
Milkomeda
Sen-Rookie-Sational
Posts: 20
Joined: Sun May 05, 2013 8:24 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#211 Post by Milkomeda » Sun May 05, 2013 8:32 pm

I think its getting modified because the underpass begins at the Goodwood Station and the Noarlunga Line starts to go below ground level at the station.

fabricator
Legendary Member!
Posts: 537
Joined: Mon Oct 27, 2008 9:13 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#212 Post by fabricator » Sat May 11, 2013 8:00 pm

neoballmon wrote: Goodwood Station, has been taken apart a little (getting shortened? replaced? or just to improve construction vehicle access?)
Image
Was done earlier to place sections of the stormwater diversion tunnel into place. They would have done a much neater job if it were proper demolition, not sure when they plan to fix it though.
AdelaideNow: Now with 300% more Liberal Party hacks, at no extra cost.

Shahkar
High Rise Poster!
Posts: 380
Joined: Wed Dec 26, 2012 2:22 am
Location: Adelaide CBD

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#213 Post by Shahkar » Tue May 14, 2013 4:54 pm


User avatar
Vee
Legendary Member!
Posts: 1105
Joined: Tue Nov 18, 2008 8:26 pm
Location: Eastern Suburbs

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#214 Post by Vee » Tue Jul 02, 2013 11:25 am

Another infrastructure milestone on the way to transforming our metropolitan railway network.
Goodwood rail services upgrade nearing completion

The major work is now finished for the underpass designed to improve rail services through the Goodwood area in Adelaide's southern suburbs.
Transport and Infrastructure Minister Tom Koutsantonis said new track was now being laid through the Goodwood Junction underpass.

"Once open to traffic, we will have separated passenger and freight lines to allow for better running on the Belair and Noarlunga services, as well as reducing delays on Cross Road," he said.

The Belair rail service is to resume in a fortnight and Noarlunga services in September.
The Government plans to have electric railcars operating the extended service to Seaford early next year.

The new underpass is 550 metres long and the junction upgrade is expected to cost $110 million.

The minister said more than 250 jobs had been created by the work and it would give Adelaide a key piece of transport infrastructure for many years to come.

http://www.abc.net.au/news/2013-07-02/g ... section=sa

jase111
Gold-Member ;)
Posts: 98
Joined: Tue Jun 01, 2010 4:20 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#215 Post by jase111 » Mon Jul 15, 2013 6:35 pm

Timetable
Construction of the Goodwood Junction underpass commenced in January 2013, and is expected to be completed September 2013.

Construction of the Wayville Station commenced in May 2013 and is expected to be completed in November 2013.

Construction timing for the Torrens Junction and Leader Street grade separations are yet to be determined.

Just saw this on nation building site would they have to close the rail again in 15/16 ?

User avatar
jk1237
Donating Member
Donating Member
Posts: 1756
Joined: Wed Jan 17, 2007 11:22 pm
Location: Adelaide

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#216 Post by jk1237 » Mon Jul 15, 2013 6:53 pm

jase111 wrote:Timetable
Construction of the Goodwood Junction underpass commenced in January 2013, and is expected to be completed September 2013.

Construction of the Wayville Station commenced in May 2013 and is expected to be completed in November 2013.

Construction timing for the Torrens Junction and Leader Street grade separations are yet to be determined.

Just saw this on nation building site would they have to close the rail again in 15/16 ?
oh please no. I bet anything they will find a way to easily keep the interstate line open, but close the Outer Harbour suburban line for a year minimum.

And that really seems a long time to build a basic station, considering they put the concrete edges of the platforms in at Wayville in about 2 weeks. Is it rare, ultra special dirt needed to fill in the platforms with?

OK I will stop whinging now

User avatar
metro
Legendary Member!
Posts: 970
Joined: Mon Sep 21, 2009 10:11 pm
Location: Sydney

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#217 Post by metro » Mon Jul 15, 2013 8:52 pm

jk1237 wrote:
jase111 wrote:Timetable
Construction of the Goodwood Junction underpass commenced in January 2013, and is expected to be completed September 2013.

Construction of the Wayville Station commenced in May 2013 and is expected to be completed in November 2013.

Construction timing for the Torrens Junction and Leader Street grade separations are yet to be determined.

Just saw this on nation building site would they have to close the rail again in 15/16 ?
oh please no. I bet anything they will find a way to easily keep the interstate line open, but close the Outer Harbour suburban line for a year minimum.

And that really seems a long time to build a basic station, considering they put the concrete edges of the platforms in at Wayville in about 2 weeks. Is it rare, ultra special dirt needed to fill in the platforms with?

OK I will stop whinging now
So far for line closures we've had:

- The Belair line has stacked up a year of track closures for replacement of the tracks and minor station improvements.
- The Tonsley line closed for over 2 years with no tracks replaced.
- The Noarlunga line closed for over a year with tracks replaced, a few stations rebuilt and an underpass constructed at Goodwood.
- The Outer Harbor line partially closed for 7 months to complete some upgrades to Port Adelaide Station.
- The Gawler line partly closed for about a year with all tracks replaced, 3 stations receiving minor improvements, 2 stations completely rebuilt and the main rail depot re-located to Dry Creek.
- Adelaide Station Closed for over a month to do something that any other city would have done over a weekend.

and here is my prediction for the next round of track closures:

- The Outer Habor/Grange will be closed for 8 months to construct the elevated Croydon Station and South Rd Rail Bridge.
- All lines - terminating before reaching the city for a couple of months for the construction of new medical school facilities west of Morphett St and to install those escalators at the southern end of the concourse, similar to the 2013 Jan/Feb closure.
- Outer Harbor and Grange lines entirely closed for 12 months to build bowden sunken station and torrens jctn.
- Gawler line closed for 6-8 months to electrify and build torrens jctn (but not-in-service trains will still be allowed through to keep the other lines going)

and Perth is making a big deal about a few days of disruption to their network for a massive rebuilding of their city station


muzzamo
Legendary Member!
Posts: 1029
Joined: Tue Aug 21, 2007 4:44 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#218 Post by muzzamo » Mon Jul 15, 2013 9:20 pm

What are the escalators at the southern concourse about?

User avatar
metro
Legendary Member!
Posts: 970
Joined: Mon Sep 21, 2009 10:11 pm
Location: Sydney

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#219 Post by metro » Mon Jul 15, 2013 9:41 pm

muzzamo wrote:What are the escalators at the southern concourse about?
it was in the budget I think..

http://dpti.sa.gov.au/newconnections/article?item=289
The State Budget also provides $3million over the next two years to reconfigure the great hall of the Adelaide Railway Station, including installing escalators.

User avatar
Norman
Donating Member
Donating Member
Posts: 6488
Joined: Sun Mar 25, 2007 1:06 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#220 Post by Norman » Mon Jul 15, 2013 9:42 pm

The Tonsley line closed for over 2 years with no tracks replaced.
Not true. The only closure has been the one since February 2012.
All lines - terminating before reaching the city for a couple of months for the construction of new medical school facilities west of Morphett St and to install those escalators at the southern end of the concourse, similar to the 2013 Jan/Feb closure.
Why? The main reason the main station was closed for a month was to allow the main junction in the city to be completely replaced.

User avatar
metro
Legendary Member!
Posts: 970
Joined: Mon Sep 21, 2009 10:11 pm
Location: Sydney

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#221 Post by metro » Mon Jul 15, 2013 10:04 pm

Norman wrote:Why? The main reason the main station was closed for a month was to allow the main junction in the city to be completely replaced.
Why not? there's still a lot of old track to replace in the Adelaide yard, and new medical facilities to build over the tracks as well.

User avatar
Norman
Donating Member
Donating Member
Posts: 6488
Joined: Sun Mar 25, 2007 1:06 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#222 Post by Norman » Tue Jul 16, 2013 12:30 am

metro wrote:
Norman wrote:Why? The main reason the main station was closed for a month was to allow the main junction in the city to be completely replaced.
Why not? there's still a lot of old track to replace in the Adelaide yard, and new medical facilities to build over the tracks as well.
Then they can just close a few platforms while the tracks are being replaced, that doesn't require a full station closure. Neither would constructing buildings over the track, as happened with the Convention Centre

claybro
Super Size Scraper Poster!
Posts: 2429
Joined: Mon Jun 18, 2012 9:16 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#223 Post by claybro » Tue Jul 16, 2013 10:39 am

Norman wrote:
metro wrote:
Norman wrote:Why? The main reason the main station was closed for a month was to allow the main junction in the city to be completely replaced.
Why not? there's still a lot of old track to replace in the Adelaide yard, and new medical facilities to build over the tracks as well.
Then they can just close a few platforms while the tracks are being replaced, that doesn't require a full station closure. Neither would constructing buildings over the track, as happened with the Convention Centre
Norman, I think the point is here, we have allowed station and line closures for lengthy time at will, they have us all accepting it now, so there is no reason to think in future, when major work is required they will bother with the logistics of juggling lines/ platforms. And re the Tonsley line closure, if it closed in Feb 2012, by the time it reopens it will have been closed for near enough to 2 years, and who knows how much longer now the upgraded stations have been proposed. Given that Perth is managing to underground its entire main station with minimal disruption, not just move some junctions and install wires, I think we are entitled to ask some questions, and demand a better solution that closing down entire lines and Adelaide station in future.

fabricator
Legendary Member!
Posts: 537
Joined: Mon Oct 27, 2008 9:13 pm

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#224 Post by fabricator » Thu Jul 18, 2013 2:39 pm

During construction work to replace track running through Goodwood Station, the platform wall on the Eastern most side of the station was undermined. When heavy rain hit the resulting flooding caused a collapse, I've seen pictures, about 10m of concrete wall has fallen over. Looks like a lot more work to do before Noarlunga trains are running again.
AdelaideNow: Now with 300% more Liberal Party hacks, at no extra cost.

User avatar
Xaragmata
Super Size Scraper Poster!
Posts: 1613
Joined: Thu Jul 19, 2007 2:08 pm
Location: Adelaide / West
Contact:

[COM] Re: U/C: Goodwood Junction Rail Underpass | $110m

#225 Post by Xaragmata » Thu Aug 01, 2013 2:12 am

Pics from Monday:

Image


Image


Image


Image