[COM] 11 Frome Street | 138m | 37 Levels | Crowne Plaza / Adelaidean | New tallest
-
- Legendary Member!
- Posts: 870
- Joined: Sun Jul 15, 2007 5:51 pm
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Nort made a good post
What is actually going on
To me it's still swp
Sent from my GT-S7275T using Tapatalk
What is actually going on
To me it's still swp
Sent from my GT-S7275T using Tapatalk
- timtam20292
- Legendary Member!
- Posts: 1459
- Joined: Tue Apr 19, 2016 1:03 pm
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
I said it's under construction to me earlier but now that I've thought about it, any demolition still means SWP. Perhaps once the crane is up then we can say under construction.
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
See the guide pinned to this forum. This is site works in progress until there’s actually a building rising.
Keep Adelaide Weird
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Thank you.SRW wrote: ↑Wed Jan 10, 2018 8:19 pmSee the guide pinned to this forum. This is site works in progress until there’s actually a building rising.
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Settle you sloppy cheese burgerHiTouch wrote: ↑Wed Jan 10, 2018 6:27 pmEase up lads, at least I’m not a racist or an argumentative piece of junk food
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Hasn't a new structure / core box looking thing gone up on the old Rhino Room site? True there's no crane on site as yet but looks like a very active construction going on to me either side of the carpark driveway.
Any views and opinions expressed are of my own, and do not reflect the views or opinions of any organisation of which I have an affiliation with.
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
timtam20292 wrote: ↑Wed Jan 10, 2018 6:43 pmI said it's under construction to me earlier but now that I've thought about it, any demolition still means SWP. Perhaps once the crane is up then we can say under construction.
I'd look at it this way.
Let's imagine they go bust right now and everything stops and the site sits in limbo for 10 years.
Would we in 10 years time look at the site and say "there is the partially constructed Adelaidean"? or would we look at it like the North Adelaide Le-Cornu site and say "there's the empty block that was intended for _______"?
Right now I think it would be the latter, so technically not yet UC.
-
- High Rise Poster!
- Posts: 293
- Joined: Thu Jul 06, 2017 11:35 am
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
I beg to differ. The definition supplied isNort wrote: ↑Thu Jan 11, 2018 1:03 amtimtam20292 wrote: ↑Wed Jan 10, 2018 6:43 pmI said it's under construction to me earlier but now that I've thought about it, any demolition still means SWP. Perhaps once the crane is up then we can say under construction.I'd look at it this way.
Let's imagine they go bust right now and everything stops and the site sits in limbo for 10 years.
Would we in 10 years time look at the site and say "there is the partially constructed Adelaidean"? or would we look at it like the North Adelaide Le-Cornu site and say "there's the empty block that was intended for _______"?
Right now I think it would be the latter, so technically not yet UC.
U/C: Under Construction
- actual building progress is being made
A building structure on site (albeit unclear as to exactly what it is) has been constructed, there is no reason to believe it is not part of the main structure as it is within the bounds of the construction site, therefore U/C seems the right description to me.
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
It's very unusual how this project being constructed at the moment. One half is basically a construction site, whilst the other half is a demolition site. Smack bang in the middle is a roadway. I think for now, it's best to leave it at SWP.
Btw with Dwell crane's increased height, it gives you a very good indication of the sheer impact Adelaidean will have on the skyline. In particular you can see the crane from the western end of Rundle Mall.
Btw with Dwell crane's increased height, it gives you a very good indication of the sheer impact Adelaidean will have on the skyline. In particular you can see the crane from the western end of Rundle Mall.
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
I could definitely be wrong, but there was basically no footings work done for the structure that has been built - I would be extremely surprised if it was part of the base for a 37 storey building.GrowAdelaide wrote: ↑Thu Jan 11, 2018 9:53 amI beg to differ. The definition supplied isNort wrote: ↑Thu Jan 11, 2018 1:03 amtimtam20292 wrote: ↑Wed Jan 10, 2018 6:43 pmI said it's under construction to me earlier but now that I've thought about it, any demolition still means SWP. Perhaps once the crane is up then we can say under construction.I'd look at it this way.
Let's imagine they go bust right now and everything stops and the site sits in limbo for 10 years.
Would we in 10 years time look at the site and say "there is the partially constructed Adelaidean"? or would we look at it like the North Adelaide Le-Cornu site and say "there's the empty block that was intended for _______"?
Right now I think it would be the latter, so technically not yet UC.
U/C: Under Construction
- actual building progress is being made
A building structure on site (albeit unclear as to exactly what it is) has been constructed, there is no reason to believe it is not part of the main structure as it is within the bounds of the construction site, therefore U/C seems the right description to me.
-
- High Rise Poster!
- Posts: 293
- Joined: Thu Jul 06, 2017 11:35 am
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Wont keep quoting previous posts as it's getting a bit long. Re the last comment though, they previously dug down a good two metres here and there is a significant pile, amongst a number of others already set, right in the middle of the floor inside the structure. Will try to get a photo at some stage.
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Id think most of demolition will be complete by the weekend.
-
- High Rise Poster!
- Posts: 293
- Joined: Thu Jul 06, 2017 11:35 am
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
I still believe this constitutes construction but not attached to the idea. Now my question is "What IS this?
- Attachments
-
- IMG_1452.JPG (914.62 KiB) Viewed 2817 times
-
- IMG_1451.JPG (698.35 KiB) Viewed 2817 times
-
- IMG_1450.JPG (855.93 KiB) Viewed 2817 times
- timtam20292
- Legendary Member!
- Posts: 1459
- Joined: Tue Apr 19, 2016 1:03 pm
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
That makes me want to say “under construction” too. Yeah what is it?
[COM] Re: Adelaidean | 11 Frome Street | 135m | 37 Levels | Mixed Use | New tallest
Looking at the plans below, it's a stairwell for the podium section.
As the full height tower is located above the section currently being demolished and just over the car park access, full height structural piling would not have commenced. I'm assuming it will do once the site is clear.
As the stairwell is part of the podium proper, I feel this can be classified as U/C.
As the full height tower is located above the section currently being demolished and just over the car park access, full height structural piling would not have commenced. I'm assuming it will do once the site is clear.
As the stairwell is part of the podium proper, I feel this can be classified as U/C.