[U/C] Re: North-South Motorway

#2956 Post by Hooligan » Fri Aug 31, 2018 6:36 pm

Any word on when T2T will open?

Code: Select all

Signature removed 

SBD
Super Size Scraper Poster!
Posts: 2708
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: North-South Motorway

#2957 Post by SBD » Fri Aug 31, 2018 7:08 pm

how good is he wrote:
Fri Aug 31, 2018 6:10 pm
I’m no expert on the traffic flows of Pym St but don’t understand why the traffic from this side street (rather than attempting to cross South Rd) can’t be directed to Torrens Rd or Regency Rd? Ridiculous to have traffic lights stopping traffic so near the start/exit of the underpass/ freeway.
I agree with Pistol, the trench should continue the extra 200m if crossing there is such a big deal.
The original plan for T2T retained the traffic lights at Torrens Road as well. The scope extended to remove those lights as part of the detailed design, I think it was even after the tender had been accepted. Continuing under Torrens Road makes it more obvious where the end of the freeway will be. If "they" had found a few more million dollars and continued under Pym Street as well, we'd be complaining about having a traffic light pedestrian crossing at the end of the freeway.

There is not presently a bus route along that section of South Road, but there is one across it on Pym Street. If all the passengers who cross South Road are going to/from the city, then it's fairly easy to reconfigure the routes so that they don't need to cross there, but if it is used by people travelling between one side of Croydon Park and the other, a different solution might be needed.

Patrick_27
Super Size Scraper Poster!
Posts: 2555
Joined: Tue Mar 05, 2013 4:41 pm
Location: Adelaide CBD, SA

[U/C] Re: North-South Motorway

#2958 Post by Patrick_27 » Fri Aug 31, 2018 11:40 pm

Portable illuminated signs up along the T2T section saying that there will be major disruptions from Sept 4-9, I *suspect* this period will see the resurfacing of South Road (the non-lowered section of road), after all, if you look at the gutters the bitumen doesn't yet level up which usually means there's one last layer to come.

aaronjameslange
Gold-Member ;)
Posts: 74
Joined: Mon Apr 06, 2015 6:53 pm

[U/C] Re: North-South Motorway

#2959 Post by aaronjameslange » Sat Sep 01, 2018 6:51 am

Patrick_27 wrote:
Fri Aug 31, 2018 11:40 pm
Portable illuminated signs up along the T2T section saying that there will be major disruptions from Sept 4-9, I *suspect* this period will see the resurfacing of South Road (the non-lowered section of road), after all, if you look at the gutters the bitumen doesn't yet level up which usually means there's one last layer to come.
According to t2t website:

Major pavement works at the South Road intersection with Port Road, and on Port Road between Queen Street and Coglin Street.

· Gantry installation in southbound lanes of South Road between Hawker Street and Port Road.

Yes most, if not all of the surface road needs a final layer. This is saved until last so all the constructruction line marking is not visible on the final product. After the final layer of bitumen will be final linemarking and thats it
Last edited by aaronjameslange on Sat Sep 01, 2018 7:29 am, edited 1 time in total.

aaronjameslange
Gold-Member ;)
Posts: 74
Joined: Mon Apr 06, 2015 6:53 pm

[U/C] Re: North-South Motorway

#2960 Post by aaronjameslange » Sat Sep 01, 2018 7:27 am

Hooligan wrote:
Fri Aug 31, 2018 6:36 pm
Any word on when T2T will open?
From a news.com.au article dated Jan 9:

THE Torrens to Torrens upgrade of South Rd will be finished by the end of September, three months ahead of schedule.
The new roadway will open earlier than expected and come in $95 million under the originally forecast $896 million budget, Transport and Infrastructure Minister Stephen Mullighan said on Tuesday.

"This project was due to be completed by the very end of 2018, the end of this year. Now the estimated completion date is by the end of September,” Mr Mullighan said.

ml69
Legendary Member!
Posts: 1005
Joined: Mon Jan 03, 2011 11:16 pm
Location: Adelaide SA

[U/C] Re: North-South Motorway

#2961 Post by ml69 » Sat Sep 01, 2018 9:24 am

aaronjameslange wrote:
Sat Sep 01, 2018 7:27 am
Hooligan wrote:
Fri Aug 31, 2018 6:36 pm
Any word on when T2T will open?
From a news.com.au article dated Jan 9:

THE Torrens to Torrens upgrade of South Rd will be finished by the end of September, three months ahead of schedule.
The new roadway will open earlier than expected and come in $95 million under the originally forecast $896 million budget, Transport and Infrastructure Minister Stephen Mullighan said on Tuesday.

"This project was due to be completed by the very end of 2018, the end of this year. Now the estimated completion date is by the end of September,” Mr Mullighan said.
Are they still on track for end of Sep opening date? That's an article from nearly 8 months ago ...

Waewick
Super Size Scraper Poster!
Posts: 3774
Joined: Tue Jun 10, 2008 1:39 pm

[U/C] Re: North-South Motorway

#2962 Post by Waewick » Sat Sep 01, 2018 10:02 am

I drive past in daily, not being a road expert you can take by view with a grain of salt.

But if there wasn't bariers up, id drive on it.


Looks very close.

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6380
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: North-South Motorway

#2963 Post by rev » Sat Sep 01, 2018 11:31 am

A lot of the surface road still needs the final bitumen layers.
Some of the intersections still need their finishing touches, like Torrens road...I assume there will be a curb in the middle..the right turn lanes look like they'll be a lot longer then they used to be. Pretty much needs new curbing/islanding in the middle all the way to Days Road..

A lot can happen in a month.

SBD
Super Size Scraper Poster!
Posts: 2708
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: North-South Motorway

#2964 Post by SBD » Sat Sep 01, 2018 11:46 am

I received email this morning about the project. It will have a public open day on Sunday 23 September. details

Construction newsletter number 9 says the motorway will open in October, but also talks about staged opening, and two fairly major closures once it has been open, those will be the final layers on the surface road and on/off ramps. So it might be "open" during daytime of the last week or two of September, with reduced speed limits and night/weekend closures for more finishing touches, but won't be open until some time in October, and the project won't be complete (landscaping, finishing touches) until nearly the end of the year.

Hooligan
Legendary Member!
Posts: 906
Joined: Tue Jul 28, 2009 8:03 pm

[U/C] Re: North-South Motorway

#2965 Post by Hooligan » Sat Sep 01, 2018 4:06 pm

Another question, Considering the issues that have been happening on the southern expressway with rock throwers, what is being done here to stop copycats?

Having driven past T2T today it looks pretty easy if someone was inclined to cause havoc.

Code: Select all

Signature removed 

mawsonguy
High Rise Poster!
Posts: 197
Joined: Fri Dec 20, 2013 8:11 am

[U/C] Re: North-South Motorway

#2966 Post by mawsonguy » Sat Sep 01, 2018 4:36 pm

It would be nice if they let you cycle\walk through the entire length of the lowered motorway at the open day on 23 September 2018 (like they did with the Superway). If they are still working on the motorway on that day, surely they can confine the work to just one side leaving the other side open for the pedestrians\cyclists.

Waewick
Super Size Scraper Poster!
Posts: 3774
Joined: Tue Jun 10, 2008 1:39 pm

[U/C] Re: [U/C] Re: North-South Motorway

#2967 Post by Waewick » Sat Sep 01, 2018 6:11 pm

Hooligan wrote:Another question, Considering the issues that have been happening on the southern expressway with rock throwers, what is being done here to stop copycats?

Having driven past T2T today it looks pretty easy if someone was inclined to cause havoc.
There are no large rocks anywhere near the place.

Also hard to throw and hide.

SBD
Super Size Scraper Poster!
Posts: 2708
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: North-South Motorway

#2968 Post by SBD » Sat Sep 01, 2018 10:55 pm

mawsonguy wrote:
Sat Sep 01, 2018 4:36 pm
It would be nice if they let you cycle\walk through the entire length of the lowered motorway at the open day on 23 September 2018 (like they did with the Superway). If they are still working on the motorway on that day, surely they can confine the work to just one side leaving the other side open for the pedestrians\cyclists.
The brochure for the open day says
http://www.t2talliance.com.au/wp88/wp-content/uploads/T2T-Major-Community-Celebration-Invitation-23-September-2018.pdf wrote:Visit the T2T website to learn more about an
opportunity to cycle or walk through the lowered
motorway on the morning of the event.
The website says
http://www.t2talliance.com.au/community-celebration-sunday-23-september-2018-11am-3pm/ wrote:More information about cycling and walking through the lowered motorway on the morning of the event will be available here after Friday 7 September 2018.
I think that suggests it will be possible, before the main crowd shows up, but they haven't worked out the details yet.

Brucetiki
Legendary Member!
Posts: 995
Joined: Tue Apr 17, 2012 6:20 pm

[U/C] Re: North-South Motorway

#2969 Post by Brucetiki » Sun Sep 02, 2018 3:52 pm

SBD wrote:
Sat Sep 01, 2018 11:46 am
I received email this morning about the project. It will have a public open day on Sunday 23 September. details

Construction newsletter number 9 says the motorway will open in October, but also talks about staged opening, and two fairly major closures once it has been open, those will be the final layers on the surface road and on/off ramps. So it might be "open" during daytime of the last week or two of September, with reduced speed limits and night/weekend closures for more finishing touches, but won't be open until some time in October, and the project won't be complete (landscaping, finishing touches) until nearly the end of the year.
Interesting choice to host it on SANFL Grand Final day

Brucetiki
Legendary Member!
Posts: 995
Joined: Tue Apr 17, 2012 6:20 pm

[U/C] Re: North-South Motorway

#2970 Post by Brucetiki » Sun Sep 02, 2018 3:59 pm

mawsonguy wrote:
Sat Sep 01, 2018 4:36 pm
It would be nice if they let you cycle\walk through the entire length of the lowered motorway at the open day on 23 September 2018 (like they did with the Superway). If they are still working on the motorway on that day, surely they can confine the work to just one side leaving the other side open for the pedestrians\cyclists.