by OlympusAnt » Sun Mar 17, 2019 10:08 pm
PD2/20 wrote: ↑Sun Mar 17, 2019 8:34 pm
OlympusAnt wrote: ↑Sun Mar 17, 2019 6:07 pm
In Melbourne, they'd have the works done in 3 days.
But here, they gotta stretch it out for more money for workers.
The March newsletter from the Project is now out
https://ptpa-public-assets.s3.amazonaws ... letter.pdf. The accompanying email specifically mentions crews working 24/7 across the site duting the closure period. The newsletter (p.4) spells out in detail the scope of work during the closure. Of note is the first item, final excavations and the construction of retaining walls. Even Melbourne can't do that sort of work in a three day timescale!!
Excavations take time, yes. I'll stand corrected on that one
Follow me on Flickr
http://www.flickr.com/photos/135625678@N06/
-
Aidan
- Super Size Scraper Poster!
- Posts: 2143
- Joined: Fri Dec 08, 2006 3:10 am
- Location: Christies Beach
#737
Post
by Aidan » Sun Mar 17, 2019 11:20 pm
I don't know why the occupation has blown out to three weeks, but the Advertiser is right to criticise it. 'Twas originally planned to be much less time, though I can't remember exactly how much less.
Most of the excavations and retaining walls are already done — there's only a little bit at the ends still to do. Should take a few days, bur not weeks.
If you think three weeks is reasonable, consider how long it takes you to change a tyre. Then consider how long it takes a Formula 1 pit crew to change a tyre. Things can be done very quickly when you're well organized.
As for how long it would take in Melbourne, I've no idea, but I very much doubt it changes according to the party in government.
Just build it wrote:Bye Union Hall. I'll see you in another life, when we are both cats.
-
Waewick
- Super Size Scraper Poster!
- Posts: 3774
- Joined: Tue Jun 10, 2008 1:39 pm
#738
Post
by Waewick » Mon Mar 18, 2019 12:38 am
Aidan wrote:I don't know why the occupation has blown out to three weeks, but the Advertiser is right to criticise it. 'Twas originally planned to be much less time, though I can't remember exactly how much less.
Most of the excavations and retaining walls are already done — there's only a little bit at the ends still to do. Should take a few days, bur not weeks.
If you think three weeks is reasonable, consider how long it takes you to change a tyre. Then consider how long it takes a Formula 1 pit crew to change a tyre. Things can be done very quickly when you're well organized.
As for how long it would take in Melbourne, I've no idea, but I very much doubt it changes according to the party in government.
3 weeks isn't reasonable becuase a team in the F1 can change a tyre quicker than i can change my tyre.
Surely if we are going to be critical, we need to have something more compelling that this?
-
mattwinter
- High Rise Poster!
- Posts: 134
- Joined: Wed May 29, 2013 3:21 pm
#739
Post
by mattwinter » Mon Mar 18, 2019 1:07 pm
The closure will inconvenice me, but honestly 3 weeks is fine. A few years ago we had a year or closures and the Tonsley line was out of action for two or three years....
They also don't bring F1 pit crews into do local go karting events. Adelaide is not a place where we have millions of people relying on our trains, so three weeks is pretty appropriate as far as I'm concerned.
-
AG
- VIP Member
- Posts: 2093
- Joined: Thu Jul 21, 2005 9:44 am
- Location: Adelaide SA
#741
Post
by AG » Mon Mar 18, 2019 2:52 pm
If you look through the scope of works outlined in the March newsletter, then it becomes apparent that the rail closure period is also being used to undertake other upgrades further along the rail corridor beyond where the Oaklands crossing upgrade is being finished.
-
SouthAussie94
- Legendary Member!
- Posts: 583
- Joined: Tue Mar 27, 2012 10:03 pm
- Location: Southern Suburbs
#742
Post
by SouthAussie94 » Tue Mar 19, 2019 11:03 am
"All we are is bags of bones pushing against a self imposed tide. Just be content with staying alive"
Views and opinions expressed are my own and don't necessarily reflect the views or opinions of any organisation of which I have an affiliation
-
flat04
- Gold-Member ;)
- Posts: 60
- Joined: Mon Jun 21, 2010 4:18 pm
#743
Post
by flat04 » Tue Mar 19, 2019 1:40 pm
Am I missing something, how does the Oaklands Crossing cause any disruption to the Tonsley line?
To give my 2 cents worth three weeks to connect in the new rail is ridiculous. What part of it can possibly take that long that can't be done prior while the existing line is still open?
-
Goodsy
- Legendary Member!
- Posts: 1107
- Joined: Thu Jul 18, 2013 10:39 am
#744
Post
by Goodsy » Tue Mar 19, 2019 2:45 pm
flat04 wrote: ↑Tue Mar 19, 2019 1:40 pm
Am I missing something, how does the Oaklands Crossing cause any disruption to the Tonsley line?
To give my 2 cents worth three weeks to connect in the new rail is ridiculous. What part of it can possibly take that long that can't be done prior while the existing line is still open?
They'll need to turn the overhead lines off, and the substation is in Londsale so it can't be isolated from the Seaford line
-
mattwinter
- High Rise Poster!
- Posts: 134
- Joined: Wed May 29, 2013 3:21 pm
#745
Post
by mattwinter » Tue Mar 19, 2019 3:35 pm
Goodsy wrote: ↑Tue Mar 19, 2019 2:45 pm
flat04 wrote: ↑Tue Mar 19, 2019 1:40 pm
Am I missing something, how does the Oaklands Crossing cause any disruption to the Tonsley line?
To give my 2 cents worth three weeks to connect in the new rail is ridiculous. What part of it can possibly take that long that can't be done prior while the existing line is still open?
They'll need to turn the overhead lines off, and the substation is in Londsale so it can't be isolated from the Seaford line
+ As AG says, there's lots of small upgrades and things being done right along the line, hence the Tonsley line can't run.
-
AndyWelsh
- Legendary Member!
- Posts: 785
- Joined: Tue Dec 19, 2017 11:44 pm
#747
Post
by AndyWelsh » Tue Apr 02, 2019 4:20 pm
Couple more:
Sent from my iPhone using Tapatalk
-
SRW
- Donating Member
- Posts: 3650
- Joined: Fri Jun 08, 2007 9:42 pm
- Location: Glenelg
#748
Post
by SRW » Tue Apr 02, 2019 5:25 pm
Looks good! Much better effort than the new Bowden station.
Keep Adelaide Weird
-
Patrick_27
- Super Size Scraper Poster!
- Posts: 2560
- Joined: Tue Mar 05, 2013 4:41 pm
- Location: Adelaide CBD, SA
#749
Post
by Patrick_27 » Tue Apr 02, 2019 5:44 pm
SRW wrote: ↑Tue Apr 02, 2019 5:25 pm
Looks good! Much better effort than the new Bowden station.
Are you kidding? Bowden looks amazing!
-
Patrick_27
- Super Size Scraper Poster!
- Posts: 2560
- Joined: Tue Mar 05, 2013 4:41 pm
- Location: Adelaide CBD, SA
#750
Post
by Patrick_27 » Tue Apr 02, 2019 5:45 pm
Any word on whether the old station shelters might be reused elsewhere? With their length, you could cover two platforms at two separate stations...