[COM] 89-109 Gray Street | 59m | 17 Levels | Student Accom
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Three photos from this weekend
I would be interested to know (from someone more experienced than me in multi storey construction) on an estimate of how long this project is from completion.
There are pretty well 4 floors of steelwork yet to be completed then the fit out. But with the (probable) low quality of internal finishing and the "drop in" bathroom and living areas etc (that may take less time than a "normal" fit out). I am guessing it is still 6 weeks for final steelwork and external cladding and then maybe another 2 -3 months after that of fit out, so that it will get practical completion sometime around mid April - May, and ready for students for the mid year intake?
I would be interested to know (from someone more experienced than me in multi storey construction) on an estimate of how long this project is from completion.
There are pretty well 4 floors of steelwork yet to be completed then the fit out. But with the (probable) low quality of internal finishing and the "drop in" bathroom and living areas etc (that may take less time than a "normal" fit out). I am guessing it is still 6 weeks for final steelwork and external cladding and then maybe another 2 -3 months after that of fit out, so that it will get practical completion sometime around mid April - May, and ready for students for the mid year intake?
- Attachments
-
- Gray st 1.JPG (2.4 MiB) Viewed 6869 times
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
looks like either floor by floor laundry areas or other ventilated space - pretty basic finishes so far
- Attachments
-
- Gray st 3.JPG (2.71 MiB) Viewed 6867 times
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Whoops...
Ground level on Gray st Mk 2
Ground level on Gray st Mk 2
- Attachments
-
- Gray st 2.JPG (2.59 MiB) Viewed 6866 times
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
In estimating construction times one should not include January as most builders and/or suppliers are on annual leave.
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Update 22/11/2019, a view from western approach to city. A vast improvement over the tied 1 and 2 story junk that was there.
- Attachments
-
- 20190122_Gray St 1.jpg (340.24 KiB) Viewed 6422 times
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
They posted on facebook yesterday this will be ready for first students in April.
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Looks like the guys from Synergy Construct have made the news yet again.... for all the wrong reason
http://www.fiveaa.com.au/shows/david-an ... ction-Site
They give good builders a bad name
http://www.fiveaa.com.au/shows/david-an ... ction-Site
They give good builders a bad name
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
That sounds like a major "oops". There's also something missing from the story - a "giant chain" doesn't "plummet down" and only break a vertical bus window without damage to the roof or other panels.borsac wrote: ↑Thu Feb 21, 2019 10:17 pmLooks like the guys from Synergy Construct have made the news yet again.... for all the wrong reason
http://www.fiveaa.com.au/shows/david-an ... ction-Site
They give good builders a bad name
It's a pity FiveAA couldn't be bothered going outside and taking a new photo. Based on the history of photos in this thread, their photo was taken some time between September 20 and October 3 last year. The tower for the hammerhead crane was up, but without a crane on it yet.
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
An up to date picture as at 23/2/2019 nearly up to full height.(on left hand side of picture).
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
26/2/2019 Picture of Some work at the ground floor level at the south end on the east side.
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Going by the following render I suspect it's just construction egress to be fitted with another wall panel as it nears completion?
Keep Adelaide Weird
-
- Legendary Member!
- Posts: 870
- Joined: Sun Jul 15, 2007 5:51 pm
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Terrible looking building
Sent from my SM-J730G using Tapatalk
Sent from my SM-J730G using Tapatalk
[COM] Re: 89-109 Gray Street | 59m | 17 Levels | Student Accom
Is that a mistake on the far right side where the panels are not zig zag?