When was the Ramada project cancelled??
Crane Counter: CBD 9 | Metro 6 | Total 15
Re: Crane Counter: CBD 9 | Metro 9 | Total 18
The commencement of construction was held on Wed 8/2/2023 with all the usual dignitaries present and a bulldozer cleared the site, but since then absolutely nothing has been done. On 25 /11/23 when I passed by the site was completely abandoned with the Ramada project sign lying on its side. So I think the turning of the first sod ceremony was a false start.
Re: Crane Counter: CBD 9 | Metro 9 | Total 18
Was that a (false) restart? The original official start was 14 April 2021. https://www.mossop.com.au/official-turn ... m-playford - interesting that Mossop still has that news story but doesn't seem to have the project anywhere else on its website.EBG wrote: ↑Wed Dec 13, 2023 12:02 pmThe commencement of construction was held on Wed 8/2/2023 with all the usual dignitaries present and a bulldozer cleared the site, but since then absolutely nothing has been done. On 25 /11/23 when I passed by the site was completely abandoned with the Ramada project sign lying on its side. So I think the turning of the first sod ceremony was a false start.
Addition: The 2021 ground breaking is also still on the Wyndham Destinations website at https://wyndhamap.com/ramada-by-wyndham ... ng-ground/
Re: Crane Counter: CBD 9 | Metro 8 | Total 17
Grenfell Street crane to come down on the 25th Feb.
Botanic high not long after.
Nothing new planned in the CBD that I can think of. Maybe Hutt Street and East Terrace although both are small enough they could be done with mobile cranes. kings head appears to be on hold.
Botanic high not long after.
Nothing new planned in the CBD that I can think of. Maybe Hutt Street and East Terrace although both are small enough they could be done with mobile cranes. kings head appears to be on hold.
Re: Crane Counter: CBD 9 | Metro 8 | Total 17
literally nothing of any height planned any time soon - I assume this is an economic indicator of somethingBen wrote: ↑Thu Feb 08, 2024 5:49 pmGrenfell Street crane to come down on the 25th Feb.
Botanic high not long after.
Nothing new planned in the CBD that I can think of. Maybe Hutt Street and East Terrace although both are small enough they could be done with mobile cranes. kings head appears to be on hold.
many of the approved proposed here have been shelved or cancelled
https://en.wikipedia.org/wiki/List_of_t ... n_Adelaide
tired of low IQ hacks
- gnrc_louis
- Legendary Member!
- Posts: 981
- Joined: Sat Nov 10, 2018 2:04 pm
- Location: Adelaide
Re: Crane Counter: CBD 9 | Metro 8 | Total 17
The Little National on North Terrace perhaps?Ben wrote: ↑Thu Feb 08, 2024 5:49 pmGrenfell Street crane to come down on the 25th Feb.
Botanic high not long after.
Nothing new planned in the CBD that I can think of. Maybe Hutt Street and East Terrace although both are small enough they could be done with mobile cranes. kings head appears to be on hold.
- SouthAussie94
- Legendary Member!
- Posts: 585
- Joined: Tue Mar 27, 2012 10:03 pm
- Location: Southern Suburbs
Re: Crane Counter: CBD 9 | Metro 8 | Total 17
17 Hutt St will have a tower crane. The base has been installed and the first precast panels of the lift shaft installed. Expect the crane in the next month or so.Ben wrote: ↑Thu Feb 08, 2024 5:49 pmGrenfell Street crane to come down on the 25th Feb.
Botanic high not long after.
Nothing new planned in the CBD that I can think of. Maybe Hutt Street and East Terrace although both are small enough they could be done with mobile cranes. kings head appears to be on hold.
"All we are is bags of bones pushing against a self imposed tide. Just be content with staying alive"
Views and opinions expressed are my own and don't necessarily reflect the views or opinions of any organisation of which I have an affiliation
Views and opinions expressed are my own and don't necessarily reflect the views or opinions of any organisation of which I have an affiliation
Re: Crane Counter: CBD 8 | Metro 8 | Total 16
Tower crane could go up this week end at 17 Hutt St - picture today (27/2/2024) shows some tower sections in place within the lift well.
Last edited by EBG on Wed Feb 28, 2024 8:23 am, edited 1 time in total.
-
- Gold-Member ;)
- Posts: 93
- Joined: Fri Jul 31, 2009 8:33 am
Re: Crane Counter: CBD 8 | Metro 8 | Total 16
Rode past 301 Pirie St this morning and Built Environ's yellow crane was onsite (disassembled). Do we know what (if anything) is happening on that site? Thanks
Re: Crane Counter: CBD 8 | Metro 8 | Total 16
The crane at 301 Pirie St is for 17 Hutt St, the builders have been using the Pirie St site as a working storage area.