#871 Post by HiTouch » Mon May 05, 2025 4:58 pm

Am I right in thinking it's taken 5 months to go up 3 storeys. Seems slow

User avatar
timtam20292
Super Size Scraper Poster!
Posts: 1564
Joined: Tue Apr 19, 2016 1:03 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#872 Post by timtam20292 » Mon May 05, 2025 5:13 pm

HiTouch wrote:
Mon May 05, 2025 4:58 pm
Am I right in thinking it's taken 5 months to go up 3 storeys. Seems slow
It’s a huge site. I was expecting extra time for the first couple of levels. Work is starting on the towers now so should go up more quickly.

I’m still not able to number the podium levels properly. Its doing my head in haha

Dvious
Legendary Member!
Posts: 664
Joined: Wed Aug 17, 2011 11:46 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#873 Post by Dvious » Mon May 05, 2025 7:01 pm

I actually feel like it's gone up fairly quickly given the size of the site.

User avatar
Pikey
VIP Member
VIP Member
Posts: 2543
Joined: Wed Jul 13, 2005 7:41 am
Location: Sitting Down

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#874 Post by Pikey » Mon May 05, 2025 9:05 pm

HiTouch wrote:
Mon May 05, 2025 4:58 pm
Am I right in thinking it's taken 5 months to go up 3 storeys. Seems slow
Not forgetting two levels of basement... To have the entire footprint covered in effectively five full levels in five months is very respectable.
Walking on over....

| Sensational-Adelaide.com Moderator |

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6641
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#875 Post by rev » Tue May 06, 2025 8:09 am

timtam20292 wrote:
Mon May 05, 2025 5:13 pm
HiTouch wrote:
Mon May 05, 2025 4:58 pm
Am I right in thinking it's taken 5 months to go up 3 storeys. Seems slow
It’s a huge site. I was expecting extra time for the first couple of levels. Work is starting on the towers now so should go up more quickly.

I’m still not able to number the podium levels properly. Its doing my head in haha
I'd take a guess and say the first level with the arches will reach up to the opening just above the hoarding in that last photo.
Then above that there seems to be two levels poured and work starting on another.
But then to the far right there seems to be another level but its hard to tell in that photo.

HiTouch
Legendary Member!
Posts: 860
Joined: Thu Feb 13, 2014 10:40 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#876 Post by HiTouch » Tue May 06, 2025 12:35 pm

Appreciate the context!

Ben
VIP Member
VIP Member
Posts: 7718
Joined: Mon Dec 19, 2005 11:46 am
Location: Adelaide

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#877 Post by Ben » Tue May 06, 2025 9:19 pm

I believe the Gouger Street side is at full height based off what I can see here the setback has started.
Attachments
IMG_3752.jpeg

User avatar
timtam20292
Super Size Scraper Poster!
Posts: 1564
Joined: Tue Apr 19, 2016 1:03 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#878 Post by timtam20292 » Wed May 07, 2025 2:11 am

Image

Ok so this is what I was remembering. The retail podium goes up to level 5 but the actual podium goes up to level 4.

Moving on!

User avatar
timtam20292
Super Size Scraper Poster!
Posts: 1564
Joined: Tue Apr 19, 2016 1:03 pm

[U/C] Central Market Arcade Redevelopment | 130m | 39 levels

#879 Post by timtam20292 » Sun May 11, 2025 8:43 pm

Image

Not sure what they’re doing here tonight, some sort of plumbing work maybe?

Edit - same works occurring on the Gouger Street side.

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6641
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#880 Post by rev » Sun May 11, 2025 10:01 pm

That looks like a vac truck.

User avatar
Bobski
High Rise Poster!
Posts: 298
Joined: Mon Dec 02, 2024 9:20 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#881 Post by Bobski » Sat May 17, 2025 3:44 pm

Progress pics 17/05


Image

Image

Image

Image

Image

Image

Image

Image

Jaymz
Legendary Member!
Posts: 1063
Joined: Sat Mar 22, 2014 5:12 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#882 Post by Jaymz » Sat May 17, 2025 4:01 pm

Thanks for the photos Bobski :cheers:

The tower proper is really starting to become obvious now 8)

User avatar
Bobski
High Rise Poster!
Posts: 298
Joined: Mon Dec 02, 2024 9:20 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#883 Post by Bobski » Sat May 17, 2025 4:16 pm

My pleasure! I'm really optimistic about this project. So so so much better than what was there before :D

Mpol02
Legendary Member!
Posts: 697
Joined: Fri Oct 16, 2020 4:06 am

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#884 Post by Mpol02 » Sat May 17, 2025 5:47 pm

A game changer for the markets and for Adelaide I hope.

Will the markets ever have to fully close while this Reno is happening?

User avatar
[Shuz]
Super Size Scraper Poster!
Posts: 3387
Joined: Sun Apr 10, 2011 5:26 pm

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

#885 Post by [Shuz] » Sun May 18, 2025 9:09 am

Mpol02 wrote:
Sat May 17, 2025 5:47 pm
A game changer for the markets and for Adelaide I hope.

Will the markets ever have to fully close while this Reno is happening?
For the umpteenth time, no.