North Terrace streetscape slow down
03Dec 08
IT HAS BEEN a North Tce eyesore for the past two-and-a-half years and is running 28 months behind schedule.
But the City Council insists the latest stage of the North Tce streetscape upgrade will be finished by Christmas.
Upgrading the 200m stretch between Pulteney St and Frome Rd has taken 29 months - averaging a snail’s-paced 1.7m a week.
The $7m upgrade, managed by Town Hall but jointly funded by the State Government, includes new paving, landscaping and a water feature near the Frome Rd corner.
The continuing works have reduced the prominent location to a cluttered mess, with barriers, large piles of dirt and pedestrian detours.
Lord Mayor Michael Harbison said the slow progress had been “frustrating”. However, he said workers had to down tools for almost 12 months while the facade of UniSA’s Brookman building was restored last year.
Funding for the upgrade only became available to the university after the North Tce roadworks had started.
“Faced with a choice between seeing the Brookman building restored or not, I think it was the right thing to do, it will be a better result for the long term,” Mr Harbison said.
He said there also had been other delays, but these had not increased the cost of the project.
“The big tree around which the water feature was designed actually shattered, fell in half, before work started, so we had to do a bit of a redesign as well.”
The upgrade is the second phase of a four-stage project redeveloping Adelaide’s premier cultural boulevard.
Comparative construction times
5 days: A full-size replica of Vienna’s Schonbrunn Palace at AAMI Stadium for the Andre Rieu concert last month
4 months: Temporary grandstands at Victoria Park for Clipsal 500
8 months: 1.6km extension to tram line from Victoria Sq to North Tce
1 year, 6 months: $1.1 billion desalination plant at Port Stanvac (State Government estimate)
2 years, 5 months: Redevelop 200m stretch of North Tce streetscape from Pulteney St to Frome Rd. Stage two was supposed to start in September 2005 and take about 11 months to complete but was delayed by funding delays. The next stage will cover the stretch in front of Government House between Kintore Ave and King William St.
[COM] North Terrace Streetscape Upgrade
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
From The Messenger:
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
Anyone want to place bets how long the next stage will take?
- Düsseldorfer
- High Rise Poster!
- Posts: 288
- Joined: Sat Sep 15, 2007 3:52 am
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
oh gawd it really took that long, and i was getting frustrated thinking it had been like that for just this year, wow, and the tram was built in much less timeShuz wrote:Anyone want to place bets how long the next stage will take?
the next stage will hopefully only take 6 months, but if the same thing happens again, probably looking at 2 years
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
Well, I'm probably most likely going to go on a photo walk around town tomorrow so I'll try and get some taken. But I don't want any pie thanks - a Cadbury Chocolate Classic should hit the spot though
- monotonehell
- VIP Member
- Posts: 5466
- Joined: Fri Feb 01, 2008 12:10 am
- Location: Adelaide, East End.
- Contact:
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
I'm still waiting on your promise of pie from last time.AtD wrote:Free pie for recent photos!
Fool me once...
Exit on the right in the direction of travel.
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
Council reckons it will be finished by christmas, yeah right
It doesn't look anywhere near finished, and they've only really started the final paving at the Frome Rd end only, no where else that Ive noticed. It will be a couple of months minimum
Maybe the ACC mean next christmas
It doesn't look anywhere near finished, and they've only really started the final paving at the Frome Rd end only, no where else that Ive noticed. It will be a couple of months minimum
Maybe the ACC mean next christmas
- monotonehell
- VIP Member
- Posts: 5466
- Joined: Fri Feb 01, 2008 12:10 am
- Location: Adelaide, East End.
- Contact:
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
They do mean next Christmasjk1237 wrote:Council reckons it will be finished by christmas, yeah right
It doesn't look anywhere near finished, and they've only really started the final paving at the Frome Rd end only, no where else that Ive noticed. It will be a couple of months minimum
Maybe the ACC mean next christmas
You mean the one after next. ;P
Exit on the right in the direction of travel.
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
29 months?!, that is an absolute disgrace
- Tyler_Durden
- High Rise Poster!
- Posts: 333
- Joined: Wed Aug 24, 2005 6:11 pm
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
I don't care how long it takes. I only care what the result looks like.
I think they did a great job with stage 1 so I have similar hopes here.
I think they did a great job with stage 1 so I have similar hopes here.
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
I have just witnessed the most amazing thing. THIS IS FINISHED. Looks like it just needs some touching up on the signs and seats, but the paving is finished and that horrible fence is gone, and its all opened up. Looks great. I might go back in and take some snaps.
[COM] Re: #U/C: North Terrace | Streetscape Upgrade Stage 2
Yeah it looks pretty good I reckon, the water feature will be pretty nice. Although they need some shading there, can't imagine many people wanting to eat their lunches in the searing heat.
Who is online
Users browsing this forum: Google Adsense [Bot] and 4 guests