Hi all
Anybody wishing to follow the progress of the Hallett Cove rebuild, i have been following it closely ( as growing up in the area, its good to see it changing for the better)
Pictures are avliable on RailSA at
http://www.railsa.org/forums/viewtopic.php?f=97&t=3570
As for the gawler line closure, At the moment Nth Adelaide station has had its base layer excavated, and the rail is missing up until Torrens Rd, with the Down line un-clipped/dogged up until Pym st. The crossover at Pym st was being re-sleepered today, and some of the contractors was telling us, the ripping up of the rail between Ovingham and Pym street will take place tomorrow.
While at Dry creek, A set of points and crossovers is sitting next the Cormack Rd crossing ready to be installed. At the Pt Wakefield Rd bridge, all track has been removed and points are starting to go in already.
This project seems to been going at steady rate and should hopefully be done ontime