[COM] UniSA - Centre for Cancer Biology | 72m | $220 million
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Some precast concrete columns have been erected on the North (RAILWAY side). The second crane base has been concreted in place.
- Attachments
-
- 20151223_Uni SA 2.jpg (355.95 KiB) Viewed 10814 times
-
- 20151223_Uni SA 1.jpg (311.83 KiB) Viewed 10814 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
The western core has started to rise up. The second crane did not go up last weekend;(too many other things on in town over the weekend). Adelaide Uni Med School up to level 8.
- Attachments
-
- 20160123_UniSA.jpg (398.62 KiB) Viewed 10286 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Looks like this will go up tomorrow or Saturday.
- Attachments
-
- image.jpeg (2.35 MiB) Viewed 10111 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
The second crane is being erected today picture 2pm. It will be the same type as the first crane.
- Attachments
-
- 20160130_135527.jpg (121.2 KiB) Viewed 9914 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Work has started to form up the ground floor level starting at the western end (next to Adel Uni med school)
- Attachments
-
- 20160204_uniSA.jpg (496.93 KiB) Viewed 9684 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
An update of the ground floor/ basement area. Note a concrete pump has been installed. 29 Feb 2016
- Attachments
-
- 20160229_Uni SA 1.jpg (451.59 KiB) Viewed 9403 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
The western core has jumped one level. the ground floor is poured in sections starting from the western(medical school) end. Some more precast Columns were being installed today closer to the Morphett St bridge.
- Attachments
-
- 20160310_UNISA 1.jpg (428.33 KiB) Viewed 9118 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Nice picture Brando where did you take it from, Somewhere high up in Hindley St ?
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Looks like it was taken from Westpac House
- Ho Really
- Super Size Scraper Poster!
- Posts: 2721
- Joined: Sun Aug 27, 2006 3:29 pm
- Location: In your head
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
More like the Commonwealth offices further down from Westpac. Can't give you the name of the building but it's the one with the atrium. Brando probably took pics of 115 KWS from there too or very close...like the car park at the back.Norman wrote:Looks like it was taken from Westpac House
Cheers
Confucius say: Dumb man climb tree to get cherry, wise man spread limbs.
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Thanks mate. As Ho Really mentioned, it was taken from the roof of Allianz building. Due to federal clients in the building, it was a task to take a quick phone camera shot.EBG wrote:Nice picture Brando where did you take it from, Somewhere high up in Hindley St ?
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
Some Precast columns have now been erected on the south side near the western core.
- Attachments
-
- 20160322_uni SA.jpg (428.01 KiB) Viewed 8118 times
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
This project is making good progress. 1.A view from North Tce side and 2. view from Morphett St bridge. Pictures taken 2 April 2016.
- Attachments
-
- 20160402_unisa 1.jpg (327.19 KiB) Viewed 7875 times
-
- 20160402_unisa 2.jpg (456.18 KiB) Viewed 7875 times
Last edited by EBG on Fri Apr 15, 2016 8:54 pm, edited 1 time in total.
[COM] Re: UniSA - Centre for Cancer Biology | 72m | $220 million
An up date view since my last picture the western core has risen one level and some more precast columns have been installed to the east (right hand side of picture).
- Attachments
-
- 20160413_uni sa 1.jpg (381.26 KiB) Viewed 7614 times
Who is online
Users browsing this forum: Majestic-12 [Bot] and 5 guests