Page 9 of 18

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Mon Jun 13, 2016 10:16 pm
by EBG
More piling being done in the basement. This part of the site looks very wet compared to the rest of the site.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Sat Jun 25, 2016 11:53 pm
by EBG
The actual basement floor was poured today. There is a service core right up against the lane way on the northern side (in front of the worker with the helicopter float) .Unfortunately I could not fit it into the picture.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Thu Jun 30, 2016 10:54 am
by Ben
I believe they have applied to add another level.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Thu Jun 30, 2016 11:54 am
by Plasmatron
Only one extra level? Oh well, beggars can't be choosers. :P

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Thu Jun 30, 2016 1:09 pm
by monotonehell
Plasmatron wrote:Only one extra level? Oh well, beggars can't be choosers. :P
Who is begging? ;P

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Wed Jul 06, 2016 8:54 pm
by Ben
Some pre fab concrete walls have been erected up to the first floor. Still no sign of a crane base and no idea where one would even go.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Thu Jul 07, 2016 8:48 am
by Pikey
Ben wrote:Some pre fab concrete walls have been erected up to the first floor. Still no sign of a crane base and no idea where one would even go.
I believe this one will have a core mounted crane.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Thu Jul 07, 2016 10:26 pm
by EBG
I agree with Pikey in that the crane could be mounted in the core. Pre cast columns were erected for the lower (of the 2 level) basement car park. Picture 7/7/16

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Sun Jul 24, 2016 9:26 pm
by EBG
This project will have 2 basement levels. Picture from Saturday 23 July shows work on the floor level between the 2 basement levels
with a service core at the bottom of the picture. Still no sign of a crane base.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Thu Jul 28, 2016 11:39 pm
by EBG
The lower floor in previous picture was concreted today Thursday 28 July.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Sat Jul 30, 2016 10:34 pm
by EBG
After the floor between the 2 basements was poured on Thursday the columns for the upper basement were installed Friday. Picture today (30/7/16)

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Sat Aug 13, 2016 3:11 pm
by citywatcher
When is the crane going up

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Sat Aug 13, 2016 11:06 pm
by EBG
Work has now reached the street level. The bondek is now in place for the ground floor and the re-inforcement is ready to be placed and and the concrete should poured this week .If the crane is to be located in the service core it should go up in the next couple of weeks (?)

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Sat Aug 20, 2016 10:27 pm
by EBG
The ground floor level was poured today (Saturday 20 /8/16). The South Tce side is less developed. with just steel work only. The service core is located in the bottom right hand corner of picture 1.

[COM] Re: 316-320 South Terrace | 49m | 14lvls | August Towers

Posted: Tue Aug 23, 2016 7:03 pm
by Wayno
Spoke with a worker this morning. Apparently no permanent crane will be used. He's unsure of the crane type to be used, but he said they are mobile and will recurringly arrive onsite when required.