Hi All
An update of works on the Noarlunga rebuild, Its a rather large post this week, so i hope some don't mind
(This post was written on anther website, by Me, yesterday)
Tamper and Ballast regulator were working down the Field River Bank today, with the Up line all tamped up until the curve on the bank, and the line ploughed and the edges leveled until the Myer Rd Overpass.
Ballasting was continuing on the Down line between the Grand Central Ave overpass and Hallett Cove Beach station. Loading of the ballast hoppers is still taking place at the Field River Bank work site until the rails are welded up to the site just south of Hallett Cove Station.
Welding crews were welding rails to the north of Hallett Cove Beach today, with 3 crews working simultaneously.
The Down line has sleepers and rail up to the old Hallett Cove Crossovers, while the Up line has rail to about halfway between Hallett Cove and The Cove Rd overpass, while sleepers were laid to Hallett Cove Station.
Laying of sleepers on the Down line was about a 1/4 of the way between hallett Cove and Marino Rocks.
At Marino Rocks, drainage crews have finished the drainage through the station, and the base layer of ballast was being laid and leveled. Crews had dug trenches for more drainage/cables around the level crossing. (i'm assuming the level crossing will be upgraded later??)
At Marino, crews have now begun removing the Asbestos cladding from the station building, while Drainage crews were completing their works around the station.
At seacliff station, no new work was noticed, with the drainage on the Up line platform still half completed.
At Brighton, crews were laying the base layer for the southern set of points, with numerous trucks dumping dolomite. Work was continuing on the station shelters, with crews re paneling the kiosk building with cement sheeting. Signal crews have placed a new heavy duty cable right across the northern yard.
The middle platform track was today receiving Geo textile matting and its first base layer was about to be started when i left.
Some photo's from this week's work's
Entrance to the Stabling Yard at Pt Stanvac.
Taming the Down line along the Field River Bank.
Ballast Regulator spreading ballast near Hallett Cove Beach.
Welding crew working through Hallett Cove Beach.
Crews working on removing Asbestos sheeting from Marino Station shelter.
Preparing the Track Bed for the southern set of Points at Brighton.
Workers replacing the Fibre Cement sheeting on the Brighton Kiosk and shelter.