[COM] Adelaide Convention Centre - Stage 3 | $350m

Posted: Fri May 27, 2016 5:32 am
by Wayno
And closer.
Image

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Fri May 27, 2016 5:29 pm
by claybro
Thanks for the photos Wayno. It is all coming along so quickly now. Still cant bring myself to like the most recent stages as much as I try not to hate on it. Just looking like a jumbled mess....but that's just me, others may love it.

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Fri May 27, 2016 6:45 pm
by Norman
In person it looks a lot better to be honest.

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Fri Jun 03, 2016 10:03 pm
by EBG
A view of the north western side as at 3 June 2016. The rear (North Tce Side) is nowhere near as complete. if this is the final colour I like it and it does tie in with the play house and the festival theatre unlike the hideous stage 2 on Morphett St .

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Mon Jun 13, 2016 10:03 pm
by EBG
The North Tce side is no where near as complete as the River front side. A picture from last Thursday (9 June 2016).

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Mon Jun 13, 2016 10:36 pm
by RiseHigh
As soon as they close this site up that's when the progress will speed up, the noise is slowing progress with the hotel next door complaining. The plan is to get the walls and roof done then there will be extra shifts around the clock to get this site moving.

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Mon Jun 13, 2016 10:47 pm
by Blimp
I quite like stage 3, its reminiscent of a menacing shark. Ties in well with the existing festival center also.

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Tue Jun 14, 2016 2:48 am
by ynotsfables
I think it's quite unique having three different looking buildings that makes up our convention centre.


Sent from my iPhone using Tapatalk

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Tue Jun 14, 2016 8:32 pm
by Pikey
The "wrap" or final cladding is being applied on the eastern side of the building. It won't be what you see on the above photos from EBG.

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Tue Jun 14, 2016 8:56 pm
by thecityguy
Pikey wrote:The "wrap" or final cladding is being applied on the eastern side of the building. It won't be what you see on the above photos from EBG.
What colour is the cladding?

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Wed Jun 15, 2016 1:26 am
by ChillyPhilly
thecityguy wrote:
Pikey wrote:The "wrap" or final cladding is being applied on the eastern side of the building. It won't be what you see on the above photos from EBG.
What colour is the cladding?
It'll be brown, if they adhere to the renders.

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Thu Jun 16, 2016 3:04 pm
by Patrick_27
ChillyPhilly wrote:
thecityguy wrote:
Pikey wrote:The "wrap" or final cladding is being applied on the eastern side of the building. It won't be what you see on the above photos from EBG.
What colour is the cladding?
It'll be brown, if they adhere to the renders.
To improve on how awful 'brown' sounds, it will be 'Copper brown'... :wink:

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Thu Jun 16, 2016 3:19 pm
by crawf
Or
Work will start next week on the building’s golden veneer cladding.

https://www.adelaidecc.com.au/3647-2/
;)

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Thu Jun 16, 2016 5:50 pm
by ChillyPhilly
Copper 'golden veneer' brown?

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Posted: Thu Jun 16, 2016 7:44 pm
by Plasmatron
Just had a look at the link crawf posted. Completion is schedule for the second half of... next year? Surely they mean this year. It looks almost finished now.