Page 13 of 43
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Wed Feb 13, 2008 4:41 pm
by Professor
They don't work the weekends on this site.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Wed Feb 13, 2008 5:24 pm
by rogue
Some tenders still need to be finalised before construction can start.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Wed Feb 13, 2008 5:40 pm
by Professor
Thanks, that explains a lot and a pity that they cannot make a good start while the weather is so good. I am looking forward to seeing the building as it gets moving.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Thu Feb 14, 2008 3:28 pm
by Pistol
Crane base going in as I type...
And it is about bloody time.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Thu Feb 14, 2008 3:29 pm
by Ben
Pistol78 wrote:Crane base going in as I type...
And it is about bloody time.
I love u
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Thu Feb 14, 2008 3:30 pm
by Pikey
Awesome!
So two new cranes in a matter of weeks for the CBD (here and Balfours)
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Thu Feb 14, 2008 3:38 pm
by teflon fox
Pistol78 wrote:Crane base going in as I type...
And it is about bloody time.
Hoo-bloody-ray ! Now when Central Park , The Inter-continental and Aurora get going Hindmarsh sq will be crane city !
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Thu Feb 14, 2008 5:19 pm
by Pistol
Ben wrote:Pistol78 wrote:Crane base going in as I type...
And it is about bloody time.
I love u
Let's just call it my valentine's gift to you...
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Thu Feb 14, 2008 5:53 pm
by skyliner
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Fri Feb 15, 2008 4:43 pm
by Howie
Hi guys, just an update from our friend James Hines from Hines Group.
You might have noticed that the crane base has been installed on the Conservatory site. A concrete pour around this base is scheduled to occur today / Monday (it may have already happened), this will then take 2 weeks to set before the crane is installed. Given the height of the crane (being one of the tallest in Adelaide for quite some time) the installation and strength required in the base set up is a serious engineering process. Otherwise all tracking well, with the piles to the perimeter of the site all but installed and the pile cap to be poured by the end of next week. The site will then be dug out to basement level with pad footings formed and the formwork trade coming on site, where we should see the structure of the building rise very fast. Given the small footprint and complexity of this development it appears like not much has been happening, but I can assure you they have been flat-out behind that site hoarding.
there's also an update on 20 hindmarsh.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Fri Feb 15, 2008 5:00 pm
by Professor
Sounds great.
Thanks for that update. A freestanding crane at that height will take some concrete in the base to keep it steady!
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Sat Feb 16, 2008 8:11 am
by Buildit
Gantries going in today
http://www.highrisegantries.com.au/
Concrete being pumped.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Sat Feb 23, 2008 6:02 pm
by UrbanSG
Nice big crane base on-site that everyone has been talking about. Pic from this afternoon:
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Mon Feb 25, 2008 9:34 am
by Edgar
FINALLY, that is all I can say!
Hopefully more actions going on in the next few weeks.
[COM] Re: #U/C: Conservatory on Hindmarsh - 62m, 18 lvls
Posted: Fri Feb 29, 2008 2:09 pm
by Pistol
Tower sections going in atm. Feel that the full crane will be up by weekends end.