Page 13 of 57

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Tue Jul 04, 2017 10:22 am
by Ben
Yep this one has always been slated for Q4 this year and as far as I know that hasn't changed.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Thu Aug 17, 2017 9:22 am
by willran
Is this the Sofitel at Luminesque, I'm looking to purchase. But had heard that it now wont be a Sofitel but some other hotel?

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Thu Aug 17, 2017 9:34 am
by Ben
Its still being advertised as a Sofitel, best way to find out is to go in to the sales centre and ask one of the guys.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Wed Aug 30, 2017 12:02 pm
by Mr Smith
Article in today's AFR in relation to the re badging of the Crown Hotel as the Pullman referenced the Sofitel and an opening date of 2019.

They will need to get a wriggle on to meet that time frame.

I spoke to a sales guy in there a while ago and he said that the Palumbo crew would be moving to this as soon as the Kent Town apartments finished, so hopefully we will see some action pretty soon on this site.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Wed Aug 30, 2017 1:20 pm
by Mr Smith
From Ben's post re 20 Hindmarsh Sq -

From 2019 Accor will also operate the city's first Sofitel hotel, a 257-room luxury venue that will be the first five-star hotel built in Adelaide in 30 years.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Thu Sep 07, 2017 4:34 pm
by Will
Got an email saying 60% of apartments have been sold, and that preliminary works are scheduled to commence in october. By preliminary works, they mean work to the infrastructure outside the site, thus enabling construction to occur.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Thu Sep 07, 2017 7:49 pm
by floplo
According to the sales guy they really try to have it up and running before Mad March 2020. Consequently I believe they currently have a little it of buffer in their schedule and will finish in late 2019 if everything goes to plan

Sent from my SM-A310F using Tapatalk


[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Mon Feb 19, 2018 4:01 pm
by Ben
Bit of a thread bump. Has anyone purchased one of these apartments? There seems to be a big delay from when they initially planned to start and realeastate.com.au still says completion Dec 2019 - obviously that won't happen.

Bit of a concern, with Sheraton and ALoft falling over.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Mon Feb 19, 2018 4:03 pm
by Allkai
No cause for concern, wheels are still turning.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Tue Feb 20, 2018 12:41 pm
by ghs
Ben wrote:
Mon Feb 19, 2018 4:01 pm
Bit of a thread bump. Has anyone purchased one of these apartments? There seems to be a big delay from when they initially planned to start and realeastate.com.au still says completion Dec 2019 - obviously that won't happen.

Bit of a concern, with Sheraton and ALoft falling over.
I know a guy who works for Palumbo and he is now saying demolition and site works in the second half of this year followed by construction early next year.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Tue Feb 20, 2018 4:53 pm
by Hybrid
Lots of service makings on the footpath out the front, and both side roads each side of the site have appeared in the last week or so. Potentially related or unrelated to the site itself.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Tue Feb 20, 2018 5:16 pm
by Jaymz
ghs wrote:
Tue Feb 20, 2018 12:41 pm
Ben wrote:
Mon Feb 19, 2018 4:01 pm
Bit of a thread bump. Has anyone purchased one of these apartments? There seems to be a big delay from when they initially planned to start and realeastate.com.au still says completion Dec 2019 - obviously that won't happen.

Bit of a concern, with Sheraton and ALoft falling over.
I know a guy who works for Palumbo and he is now saying demolition and site works in the second half of this year followed by construction early next year.
Sugar coat it however you like, but it's pretty poor since this was first mooted over 4 years ago. Not to mention it was reported on a prime time news service well over 2 years ago.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Wed Feb 28, 2018 6:30 pm
by Smithy85
Article on Tiser site.. Construction (demo) to start in May.

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Wed Feb 28, 2018 6:44 pm
by Algernon
May 21 demolition starts

[COM] Re: Currie/Rosina St | 117m | 33lvl | Sofitel

Posted: Wed Feb 28, 2018 6:46 pm
by wilkiebarkid
Demolition May 21. 80% of apartments are sold. Adelaide Now.