Page 125 of 135

Re: Crane Counter: CBD 12 | Metro 9 | Total 21

Posted: Mon May 01, 2023 10:06 pm
by EBG
Picture (1 May 23) of the 2 cranes at 88 O'Connell st. the new crane is on the left.

Re: Crane Counter: CBD 12 | Metro 9 | Total 21

Posted: Tue May 02, 2023 12:13 am
by crawf
EBG wrote:
Mon May 01, 2023 10:06 pm
Picture (1 May 23) of the 2 cranes at 88 O'Connell st. the new crane is on the left.
Never thought I'd see this day....

Re: Crane Counter: CBD 12 | Metro 9 | Total 21

Posted: Sat May 13, 2023 4:36 pm
by Prodical
One of the SAHMRI cranes came down today :(

Re: Crane Counter: CBD 11 | Metro 9 | Total 20

Posted: Sun May 14, 2023 10:04 am
by Capbld
Crane went up at Lyell Mc Yesterday

Re: Crane Counter: CBD 11 | Metro 9 | Total 20

Posted: Sun May 14, 2023 10:08 am
by luffingjib
Burnside crane 2 base was poured on Friday


Sent from my iPhone using Tapatalk

Re: Crane Counter: CBD 11 | Metro 9 | Total 20

Posted: Mon May 15, 2023 8:59 am
by SBD
Capbld wrote:
Sun May 14, 2023 10:04 am
Crane went up at Lyell Mc Yesterday
What is the current construction there?

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Mon May 15, 2023 9:14 am
by Capbld

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Mon May 15, 2023 12:27 pm
by SBD
Capbld wrote:
Mon May 15, 2023 9:14 am
Its a new 48 bed department

https://www.premier.sa.gov.au/media-rel ... sis-chairs
Thanks.

That says the new wards will be on level 3 of building A that was built as a cold shell ten years ago. It seems odd that a tower crane is required for what sounds like it is essentially an internal fitout.

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Thu May 18, 2023 12:53 pm
by urban
SBD wrote:
Mon May 15, 2023 12:27 pm
Capbld wrote:
Mon May 15, 2023 9:14 am
Its a new 48 bed department

https://www.premier.sa.gov.au/media-rel ... sis-chairs
Thanks.

That says the new wards will be on level 3 of building A that was built as a cold shell ten years ago. It seems odd that a tower crane is required for what sounds like it is essentially an internal fitout.
This is a level 3 extension to the existing building - new external walls and roof. Only 2 floors were built but there is a helipad above.

https://www.google.com.au/maps/@-34.749 ... 384!8i8192

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Sat May 27, 2023 9:48 pm
by EBG
back to 20 cranes-The southern crane (closest to North Tce) came down today at the festival plaza tower, only some tower sections remain at 5 pm Saturday 27/5/2023.

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Sat May 27, 2023 9:53 pm
by EBG
Could be back up to 21 cranes soon - picture of crane base for project on corner of Frome St and Pirie St (excuse blue shade cloth in picture.

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Sat May 27, 2023 10:02 pm
by EBG
Finally got a picture of the crane at lyelle McEwin hospital at Elizabeth

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Sun May 28, 2023 10:58 am
by Capbld
One crane coming down at TQEH today.

Re: Crane Counter: CBD 11 | Metro 10 | Total 21

Posted: Sun May 28, 2023 11:15 am
by luffingjib
Burnside crane 2 next weekend


Sent from my iPhone using Tapatalk

Re: Crane Counter: CBD 10 | Metro 9 | Total 19

Posted: Fri Jun 02, 2023 11:45 am
by EBG
tower crane sections for Burnside Village second crane going up this morning.