Page 17 of 56

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Wed May 28, 2008 11:55 am
by Pikey
That's the one!

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Thu May 29, 2008 1:08 am
by Ho Really
Pikey wrote:...Isn't the developer of this the same as iPad? Thyren?
Melbourne company the Mattioli Group are the developers of iPad.
UrbanSG wrote:I think the developer for this one is Kyren Pty Ltd who are currently constructing the Coglin development.
Yes, it's Theo Samaras.

Cheers

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Mon Jun 02, 2008 9:21 am
by UrbanSG
It looks like there may finally be some levelling of the site occurring today ready for a concrete pour for the basement in the near future. Considering this one has now been under construction for half a year we are really due for some substantial progress soon, hopefully.

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Mon Jun 02, 2008 11:20 am
by Ho Really
UrbanSG wrote:It looks like there may finally be some levelling of the site occurring today ready for a concrete pour for the basement in the near future. Considering this one has now been under construction for half a year we are really due for some substantial progress soon, hopefully.
I don't know but maybe Samaras had shortage of labour.

Cheers

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Mon Jun 02, 2008 11:27 am
by UrbanSG
The reasons why have been discussed a few pages back eg lawyer issue re: access for a neighbour which resulted in a shift of the contruction site access point, plus waiting for development approval for an amended design and work to ensure the northen boundary wall would not collapse.

Then rain came along (which should have been expected by the site manager) and made the site a muddy mess over the past couple of weeks. Hopefully they can get the site level and concreted before the next lot of rain. The number of workers on site seems to fluctuate a lot. Sometimes there are a few, other times a fair few.

I just want to see a crane or two and some steel finally going up.

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Mon Jun 02, 2008 5:24 pm
by skyliner
UrbanSG wrote:
I just want to see a crane or two and some steel finally going up.
Me too! Can hardly wait - such an impressive place and fills KWS(with highrise) much closer to the main CBD as well.

ADELAIDE - TOWARDS A GREATER CITY SKYLINE

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Wed Jun 04, 2008 12:08 am
by Ho Really
UrbanSG wrote:The reasons why have been discussed a few pages back eg lawyer issue re: access for a neighbour which resulted in a shift of the contruction site access point, plus waiting for development approval for an amended design and work to ensure the northen boundary wall would not collapse.

Then rain came along (which should have been expected by the site manager) and made the site a muddy mess over the past couple of weeks. Hopefully they can get the site level and concreted before the next lot of rain. The number of workers on site seems to fluctuate a lot. Sometimes there are a few, other times a fair few.
Yes, I understand those have been the main reasons (in particular the latter one rain). I was thinking about the absence of a foundation and the workers (who do the formwork and concrete). As we all know, when the foundation is laid the steel will go up quickly.

Cheers

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Thu Jun 05, 2008 1:17 pm
by wilkiebarkid
Pics from today. Seems more like the building site for a house with the lack of activity!

Image

Image

Image

Image

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Thu Jun 05, 2008 1:28 pm
by UrbanSG
Thanks for all the pics wilkiebrkid.

This one sure is taking a while. Look at all that water in the core pits! :roll: You can see they are levelling the site for the concrete pour. They had better hurry up though as there could be some more rain soon and rain is forecast next week too.

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Fri Jun 06, 2008 3:02 pm
by Ho Really
Did you guys notice a hose into a drain on King William Street? They've obviously got it there to pump out the water. As I don't go down there often, I was lucky enough on Tuesday as my wife and I went to Glenelg on the tram.

Cheers

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Fri Jun 06, 2008 3:06 pm
by UrbanSG
Yeah that hose has been their for a while. Didn't seem to help much over the last few weeks. The site was still waterlogged unfortunately even with that pipe.

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Sat Jun 07, 2008 12:10 pm
by Pikey
Installation of pre-fab concrete panels happening as we speak. Trucks are lined up down King william st.

I dare say that they are for the core.

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Sat Jun 07, 2008 8:41 pm
by skyliner
I was beginning to wonder if this would EVER get going. Great to hear.

ADELAIDE - TOWARDS A GREATER CITY SKYLINE

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Sun Jun 08, 2008 11:30 am
by Professor
Would really appreciate some photos of this one starting to take shape when someone has the chance.

Thanks

[COM] Re: #U/C: 374-400 King William St - 47m, 11 lvls

Posted: Sun Jun 08, 2008 11:44 am
by Howie
Professor wrote:Would really appreciate some photos of this one starting to take shape when someone has the chance.

Thanks
Shoudn't be any worries there, we've got a few super s-a super sleuths working right opposite there ;)

I'll try to get there on the weekends too.