[COM] Re: South Road Upgrade
Posted: Sat Nov 24, 2007 1:46 pm
I found the time-line of events that will occur for the underpass from http://www.adelaideconnect.com.au
TIMEFRAMES AND STAGING OF WORKS
• Construction activities started in July 2007 and are scheduled for completion by the end of 2009.
• Construction works will take place in three stages:
Stage 1: (July 2007 – Mid 2008).
Stage 2: (Mid 2008 – Mid 2009).
Stage 3: (Mid 2009 - End 2009).
STAGE 1 WORKS INCLUDE
• erection of a site office on South Road between Mortimer and Basnett Streets, Kurralta Park; building the
southern half of the 36m wide bridge deck;
• installation of noise walls and other treatments to occur in parallel with construction at each stage;
• during the same period new culverts (required to further to reduce the risk of flooding) will be placed under South
Road at Brown Hill Creek and minor storm water drainage along ANZAC Highway will be upgraded;
• excavation work on South Road on both sides of the underpass to create a ‘drive through’;
• other works commencing in this period will include a new north bound entry ramp, southern underpass
earthworks and barrier placement, and common services trenching enabling the relocation of existing Service
Authority infrastructure.
STAGE 1 TEMPORARY ROAD CLOSURES
• Temporary road closures will be implemented at times to increase safety for the general public and workers while
works are in progress and to deter vehicles from using side streets to avoid the intersection, thereby minimising
disturbance to local residents.
• In the first stage of construction, the north-west quadrant will experience temporary long term road closures in
Mortimer and Basnett Streets and Garfield Avenue. These are expected to be implemented progressively from
late September for a period of approximately 6 months.
STAGE 2 WORKS
• Key activities during Stage 2 will include:
- building the northern side of the bridge deck;
- stitching the two halves of the bridge deck together to form the ANZAC Highway ‘at grade’ bridge; and
- excavation of South Road from the northern side to complete the underpass.
• By the end of stage 2, motorists will be driving through the new underpass although not fully complete.
STAGE 3 WORKS
With the upgraded South Road on a new alignment by mid 2009, all that will be left to do during this stage will be a
makeover of South Road and surrounding areas of the intersection. These works will include:
• landscaping, including tree planting;
• completion of paving and kerbing; and
• installation of all final urban design features such as memorial plaques, feature lighting and other treatments.
So basically by mid 2009 we can use the underpass....and by end of 2009 it will be fully done.
TIMEFRAMES AND STAGING OF WORKS
• Construction activities started in July 2007 and are scheduled for completion by the end of 2009.
• Construction works will take place in three stages:
Stage 1: (July 2007 – Mid 2008).
Stage 2: (Mid 2008 – Mid 2009).
Stage 3: (Mid 2009 - End 2009).
STAGE 1 WORKS INCLUDE
• erection of a site office on South Road between Mortimer and Basnett Streets, Kurralta Park; building the
southern half of the 36m wide bridge deck;
• installation of noise walls and other treatments to occur in parallel with construction at each stage;
• during the same period new culverts (required to further to reduce the risk of flooding) will be placed under South
Road at Brown Hill Creek and minor storm water drainage along ANZAC Highway will be upgraded;
• excavation work on South Road on both sides of the underpass to create a ‘drive through’;
• other works commencing in this period will include a new north bound entry ramp, southern underpass
earthworks and barrier placement, and common services trenching enabling the relocation of existing Service
Authority infrastructure.
STAGE 1 TEMPORARY ROAD CLOSURES
• Temporary road closures will be implemented at times to increase safety for the general public and workers while
works are in progress and to deter vehicles from using side streets to avoid the intersection, thereby minimising
disturbance to local residents.
• In the first stage of construction, the north-west quadrant will experience temporary long term road closures in
Mortimer and Basnett Streets and Garfield Avenue. These are expected to be implemented progressively from
late September for a period of approximately 6 months.
STAGE 2 WORKS
• Key activities during Stage 2 will include:
- building the northern side of the bridge deck;
- stitching the two halves of the bridge deck together to form the ANZAC Highway ‘at grade’ bridge; and
- excavation of South Road from the northern side to complete the underpass.
• By the end of stage 2, motorists will be driving through the new underpass although not fully complete.
STAGE 3 WORKS
With the upgraded South Road on a new alignment by mid 2009, all that will be left to do during this stage will be a
makeover of South Road and surrounding areas of the intersection. These works will include:
• landscaping, including tree planting;
• completion of paving and kerbing; and
• installation of all final urban design features such as memorial plaques, feature lighting and other treatments.
So basically by mid 2009 we can use the underpass....and by end of 2009 it will be fully done.