[U/C] Main South Road & Victor Harbor Road Upgrade

Threads relating to transport, water, etc. within the CBD and Metropolitan area.
Message
Author
Archer
High Rise Poster!
Posts: 152
Joined: Mon Jun 09, 2008 11:44 am

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#46 Post by Archer » Mon Jan 31, 2022 3:01 pm

Further Site Investigation works as per E-Mail received today:

Fleurieu Connections
Site Investigation Works
January 2022
The Australian and South Australian governments have committed a total of $560 million to fund the Fleurieu Connections Main South Road and Victor Harbor Road duplication projects. These projects will result in safer and faster journeys for motorists and provide a vital boost for local tourism, communities and support hundreds of jobs each year during construction.

The next stage of site investigation works will commence soon and will include surveying, service location and geotechnical investigations. These works are required to better understand the existing ground conditions.

These works will occur along Main South Road (between Seaford and Aldinga), Victor Harbor Road (between Main South Road and McLaren Vale) and along Quarry and Seaview roads, McLaren Vale.

To ensure the works can be undertaken safely and efficiently, most of the works will be undertaken at night from Monday to Friday between the hours of 7pm to 6am.

Works outside the main road corridor and on side roads will be undertaken during the day from Monday to Saturday 7am to 5pm.

To safely undertake these works, speed and lane restrictions will be in place. Signage will be used to advise road users of changed traffic conditions.

Some removal of woody weeds will also be undertaken for construction, including under and around the Pedler Creek Bridge. These works will be undertaken during the day.

Access to properties and businesses will be maintained throughout the works wherever possible, with advance notice provided if there is a need to temporarily restrict driveway access. Please continue to support local businesses.

The Department appreciate your co-operation and patience while these important works are undertaken. Every effort will be made to minimise impacts to landowners and the community.

A further update about the projects will be provided shortly.

For more information, please contact the project team via phone on 1300 794 880 or email [email protected]

Kind regards

Community Engagement and Stakeholder Team

Archer
High Rise Poster!
Posts: 152
Joined: Mon Jun 09, 2008 11:44 am

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#47 Post by Archer » Tue Feb 08, 2022 10:01 am

First Newsletter from the Consortium awarded the construction contract (Fleurieu Connections Alliance) is now available: https://fcalliance.com.au/assets/volume ... y-2022.pdf

Website is also now online: https://fcalliance.com.au/

Initial Works and Detailed Design underway with Major Construction scheduled to (Finally) state Mid 2022.

State Labour has also announced additional funding of $125 Million if they win the election next month to fully duplicate between Aldinga and Sellicks as well as to re-align and Grade Separate Aldinga & Aldinga Beach Roads.
Short 7News Story here: https://www.facebook.com/watch/?v=2061194120727362 and more detail at the Main South Road Action Group's Facebook Page: https://www.facebook.com/SeafordtoSellicks (Posts from the 6th of Feb).

Batlin
Sen-Rookie-Sational
Posts: 4
Joined: Sat Feb 19, 2022 5:49 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#48 Post by Batlin » Sun Feb 20, 2022 7:14 am

[Shuz] wrote:
Mon May 10, 2021 2:42 pm
Since when has environmental impact statements ever got in the way of a politician or transport department proceeding with projects anyway?

Case in example, North East Link in Melbourne. The EIS is absolutely scathing of the project. A 16 lane freeway is still getting built anyway.
The approach to infrastructure in Victoria is very different to anywhere else I have worked. The Government in Victoria has very broad powers when it comes to infrastructure. But NELP is still subject to the EPBC Act. Part of the reason for tunnels will be to minimise approval requirements under the EPBC Act ie native vegetation offsets and impacts on Commonwealth and reduce land acquisition.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2744
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] Re: [PRO] Re: Main South Road & Victor Harbor Road Upgrade

#49 Post by ChillyPhilly » Sun Feb 20, 2022 7:27 am

Batlin wrote:
[Shuz] wrote:
Mon May 10, 2021 2:42 pm
Since when has environmental impact statements ever got in the way of a politician or transport department proceeding with projects anyway?

Case in example, North East Link in Melbourne. The EIS is absolutely scathing of the project. A 16 lane freeway is still getting built anyway.
The approach to infrastructure in Victoria is very different to anywhere else I have worked. The Government in Victoria has very broad powers when it comes to infrastructure. But NELP is still subject to the EPBC Act. Part of the reason for tunnels will be to minimise approval requirements under the EPBC Act ie native vegetation offsets and impacts on Commonwealth and reduce land acquisition.
Car culture and big, expensive road projects have always been endemic in Victoria and Melbourne.
Our state, our city, our future.

All views expressed on this forum are my own.

Batlin
Sen-Rookie-Sational
Posts: 4
Joined: Sat Feb 19, 2022 5:49 pm

[U/C] Re: [PRO] Re: Main South Road & Victor Harbor Road Upgrade

#50 Post by Batlin » Sun Feb 20, 2022 8:58 am

ChillyPhilly wrote:
Sun Feb 20, 2022 7:27 am
Batlin wrote:
[Shuz] wrote:
Mon May 10, 2021 2:42 pm
Since when has environmental impact statements ever got in the way of a politician or transport department proceeding with projects anyway?

Case in example, North East Link in Melbourne. The EIS is absolutely scathing of the project. A 16 lane freeway is still getting built anyway.
The approach to infrastructure in Victoria is very different to anywhere else I have worked. The Government in Victoria has very broad powers when it comes to infrastructure. But NELP is still subject to the EPBC Act. Part of the reason for tunnels will be to minimise approval requirements under the EPBC Act ie native vegetation offsets and impacts on Commonwealth and reduce land acquisition.
Car culture and big, expensive road projects have always been endemic in Victoria and Melbourne.
Not really. They are investing significantly in rail infrastructure. There are only two significant road projects going at the moment and a smattering of smaller ones. NELP will change that of course once it gets going. What I was referring to more was the Government's powers under the MTPFA and elsewhere to ram its projects through.

alexczarn
Gold-Member ;)
Posts: 92
Joined: Tue Nov 26, 2013 11:13 am

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#51 Post by alexczarn » Sat Mar 19, 2022 9:46 pm

Archer wrote:
Tue Feb 08, 2022 10:01 am
First Newsletter from the Consortium awarded the construction contract (Fleurieu Connections Alliance) is now available: https://fcalliance.com.au/assets/volume ... y-2022.pdf

Website is also now online: https://fcalliance.com.au/

Initial Works and Detailed Design underway with Major Construction scheduled to (Finally) state Mid 2022.

State Labour has also announced additional funding of $125 Million if they win the election next month to fully duplicate between Aldinga and Sellicks as well as to re-align and Grade Separate Aldinga & Aldinga Beach Roads.
Short 7News Story here: https://www.facebook.com/watch/?v=2061194120727362 and more detail at the Main South Road Action Group's Facebook Page: https://www.facebook.com/SeafordtoSellicks (Posts from the 6th of Feb).
guess we'll be getting that extension after all; now who wants to take on a proper Old Noarlunga bypass?

User avatar
Norman
Donating Member
Donating Member
Posts: 6487
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#52 Post by Norman » Sun Jul 10, 2022 10:17 am

I've done a video on the progress of works on Victor Harbor Road. Main South Road will be coming very soon.

https://youtu.be/mpUk0dvwh0Y

User avatar
[Shuz]
Super Size Scraper Poster!
Posts: 3289
Joined: Sun Apr 10, 2011 5:26 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#53 Post by [Shuz] » Mon Jul 11, 2022 11:01 am

Thanks Norm for the update.

This project serves well for future proofing local traffic movements particularly between McLaren Vale, Old Noarlunga and Seaford Heights.

However, what has been overlooked is the traffic movements between Adelaide and Victor Harbor. There needs to be a freeway standard road connecting these two cities. See attachment for proposed route.
Attachments
Screenshot_20220711-105604_Maps.jpg
Any views and opinions expressed are of my own, and do not reflect the views or opinions of any organisation of which I have an affiliation with.

User avatar
AG
VIP Member
VIP Member
Posts: 2093
Joined: Thu Jul 21, 2005 9:44 am
Location: Adelaide SA

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#54 Post by AG » Mon Jul 11, 2022 11:49 am

[Shuz] wrote:
Mon Jul 11, 2022 11:01 am
Thanks Norm for the update.

This project serves well for future proofing local traffic movements particularly between McLaren Vale, Old Noarlunga and Seaford Heights.

However, what has been overlooked is the traffic movements between Adelaide and Victor Harbor. There needs to be a freeway standard road connecting these two cities. See attachment for proposed route.
That straight line route from the end of the Southern Expressway to Victor Harbor Road at McLaren Vale is not as straight forward as it looks. There are large hills flanking either side of the Onkaparinga River on that alignment, so the route would require significant earthworks, bridges and/or tunnels to achieve - i.e. it's going to be very expensive per kilometre!

User avatar
[Shuz]
Super Size Scraper Poster!
Posts: 3289
Joined: Sun Apr 10, 2011 5:26 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#55 Post by [Shuz] » Mon Jul 11, 2022 2:00 pm

We moved mountains and built tunnels for the SE Freeway. No reason why it can't be done again.
Any views and opinions expressed are of my own, and do not reflect the views or opinions of any organisation of which I have an affiliation with.

Eurostar
Legendary Member!
Posts: 952
Joined: Thu Jun 24, 2010 3:44 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#56 Post by Eurostar » Mon Jul 11, 2022 11:57 pm

But building road through National Park is controversial

User avatar
Norman
Donating Member
Donating Member
Posts: 6487
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#57 Post by Norman » Tue Jul 12, 2022 7:32 am

Just finished the progress video on Main South Road as well.

Link: https://youtu.be/nQc_9CwRQng

User avatar
Spotto
Legendary Member!
Posts: 749
Joined: Wed May 15, 2019 9:05 pm

[U/C] Main South Road & Victor Harbor Road Upgrade

#58 Post by Spotto » Tue Jul 12, 2022 9:01 am

Hopefully right now they’re making a decision on duplicating through to Willunga and Sellicks and they’ll roll crews across to Stage 2 when the current duplication works begin to wind down in 2023-24.

But, that would be an sensible approach… something governments aren’t that known for

User avatar
Norman
Donating Member
Donating Member
Posts: 6487
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#59 Post by Norman » Tue Jul 12, 2022 11:26 am

Spotto wrote:
Tue Jul 12, 2022 9:01 am
Hopefully right now they’re making a decision on duplicating through to Willunga and Sellicks and they’ll roll crews across to Stage 2 when the current duplication works begin to wind down in 2023-24.

But, that would be an sensible approach… something governments aren’t that known for
The Malinauskas Government committed to duplicating Main South Road all the way to Sellicks Beach, no news on extending the Victor Harbor Road upgrade though.

SBD
Super Size Scraper Poster!
Posts: 2708
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[U/C] Re: Main South Road & Victor Harbor Road Upgrade

#60 Post by SBD » Tue Jul 12, 2022 2:51 pm

AG wrote:
Mon Jul 11, 2022 11:49 am
[Shuz] wrote:
Mon Jul 11, 2022 11:01 am
Thanks Norm for the update.

This project serves well for future proofing local traffic movements particularly between McLaren Vale, Old Noarlunga and Seaford Heights.

However, what has been overlooked is the traffic movements between Adelaide and Victor Harbor. There needs to be a freeway standard road connecting these two cities. See attachment for proposed route.
That straight line route from the end of the Southern Expressway to Victor Harbor Road at McLaren Vale is not as straight forward as it looks. There are large hills flanking either side of the Onkaparinga River on that alignment, so the route would require significant earthworks, bridges and/or tunnels to achieve - i.e. it's going to be very expensive per kilometre!
We could either bat a big suspension bridge or a viaduct with lots of columns like we see on British railway shows. Either way is mostly over the park.