Page 5 of 15
[COM]
Posted: Fri May 11, 2007 10:08 am
by rhino
Love your work Sidler
Thanks
[COM]
Posted: Fri May 11, 2007 10:17 am
by Ho Really
sidler wrote:...Sorry couldnt get much of the east side, only had access to the west.
No worries mate, you did heaps.
Cheers
[COM]
Posted: Fri May 25, 2007 11:39 pm
by warpspeed
They seem to be doing 'something' to the current intersection, it looks half done, looks like they're re-aligning it in some way. They've moved some of the traffic lights that point down Henley Beach Road.
[COM]
Posted: Sat May 26, 2007 9:34 am
by AG
Road bridge opens
TOM ZED
May 25, 2007 11:30pm
Article from: Font size: + -
Send this article: Print Email
MOTORISTS can drive over the Bakewell Underpass project from today.
The first stage of the $41 million dollar project has been completed and the road bridge over the underpass will be open to traffic and pedestrians from 10am. One lane will be open in each direction for vehicles and pedestrians to cross the section of the James Congdon Drive-East Tce bridge.
Pedestrian crossings at the intersection of Henley Beach Rd and East Tce will be moved to allow for the opening of the bridge. Temporary pedestrian signals will be installed on James Congdon Drive near Hughes St, which will operate between 8am and 4pm Monday to Friday.
The changes to traffic and pedestrian conditions will continue until the underpass is opened towards the end of the year. The final road bridge will allow two lanes of traffic in each direction, on-road bike lanes and a shared pedestrian and off-road bicycle path.
A limit of 40km/h on James Congdon Drive and East Tce near the construction site will continue.
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sat Jul 14, 2007 11:40 pm
by BillD
Southbound traffic has been prevented from travelling over the new bridge from 3am this morning (Sat 14th).
I called in three times today, twice during the day and finally at 11pm. Each time there was nothing happening but the traffic was still being diverted.
Earlier in the day I was told that the remaining bridge support was coming down. The traffic diversion is in place until Monday morning so the demolition must be some time on Sunday.
Bill
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 15, 2007 2:51 pm
by BillD
According to locals, work began on the demolition of the remaining Bakewell bridge pier at 9:30am Sunday.
There has been much speculation over the last few months as to what process would be used. In the end, a machine with what can best be described as a mega pair of snips is simply cutting it up!
Bill
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 15, 2007 6:20 pm
by bmw boy
FINALLY!!!!!!
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 15, 2007 7:30 pm
by Cruise
I wish theyed kept it, with a mural painted on it or something
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 15, 2007 8:58 pm
by Will409
I took a train to and from Belair today and made note of the work going on. The Adelaide end approach to the underpass is looking much closer to completion for a start. The tarmac from what is left at the West Terrace end of Glover Avenue can now be seen from the train.
That final pyle was looking like it was giving a fair fight since when compared to Bill's photos and when I was through there at about 5pm, not much had changed. Some more work on the corners had been done but not a lot else.
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 15, 2007 10:34 pm
by bmw boy
Cruise Control wrote:I wish theyed kept it, with a mural painted on it or something
im gonna take a leaf out of John McEnroe's book here....
YOU CANNOT BE SERIOUS!!
anyway, it would be covered in graffitti within 24 hrs of the completion of this mural...
[COM] Re: Bakewell Underpass Project - Updates
Posted: Tue Jul 17, 2007 11:23 pm
by Bulldozer
I wonder if those snips have a "WARNING: Keep fingers clear!" label on them?
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sat Jul 21, 2007 11:19 pm
by BillD
This photo was taken on the Wendnesday following last weekend's efforts and the big jack-hammer is dealing with the remaining foundations. I drove past on Saturday and couldn't see anything left.
I guess that the material in the foreground is reinforcing rod.
Bill
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 29, 2007 4:09 pm
by Norman
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Jul 29, 2007 8:36 pm
by bmw boy
had a story on the news last night.
The project is on schedule and will be ready around the end of the year
[COM] Re: Bakewell Underpass Project - Updates
Posted: Sun Sep 02, 2007 3:46 pm
by Norman