COM: Glenelg Tramline Upgrade
For the extension, it has been decided to use 'island' platforms between 4.2m (for City West, Railway Station and Victoria Square) and 3.5m wide (for Rundle Mall and Pirie Street). It is partly for passenger safety because unlike the Melbourne 'safety zones', island platforms can be intergrated into pre existing pedestrian crossings which is the plan here. When comparing the total width between the two, they are both similar.
You can easily tell where the new platforms are going to go because of the extra track width compared to normal.
You can easily tell where the new platforms are going to go because of the extra track width compared to normal.
There's a bit of an issue that seems to have arisen out of the work done on the weekend. It is regarding the changes to traffic signals and conditions at the North Terrace and King William Street intersection. There used to be a "B" signal that used to allow buses turning right from King William Street that was removed over the weekend. Numerous times I spotted near misses between buses completing the hook turn and cars turning right from North Terrace.
The affected bus routes are the F40, M44, 174, 176, 177, 178, 179 and 291.
The affected bus routes are the F40, M44, 174, 176, 177, 178, 179 and 291.
Re: Glenelg Tram Line Upgrade
Please excuse the long delay since my last extension photo update. I did get some shots from last week but I havn't found the time to get the photos up. First, photobucket is dead slow and secondly, year 12 isn't exactly time friendly! These photos are from last week. Pavement has gone into place along to median in North Terrace along with new traffic lights near Morphett Street Bridge. Also got a couple of shots of the track set in concrete. Should be a 'light load' this time with only 5 photos.
New median in North Terrace.
New lights by Morphett Street Bridge.
Rundle Mall stop site concreted in.
Pirie Street looking towards Vic Square.
New median in North Terrace.
New lights by Morphett Street Bridge.
Rundle Mall stop site concreted in.
Pirie Street looking towards Vic Square.
Re: Glenelg Tram Line Upgrade
Stage 4 of the project has been released. The work involved will be the comstruction of the curve from North Terrace into King William Street and also from King William Street to Victoria Square across Franklin Street. Rumour has it that the overhead will also start to go in this weekend as well. There are a few holes in the newly laid pavment on the median in North Terrace and I have also seen a few conduit cables sticking out of the ground near City West. I sadly will be Whyalla bound for the weekend so I cannot present my photo essay this time.
Re: Glenelg Tram Line Upgrade
Everyone will be happy to know that part of the 2007/2008 budget is a tram overpass for South Rd near the Anzac underpass. They must have realised the underpass was pointless without the tram overpass.
- jimmy_2486
- Legendary Member!
- Posts: 639
- Joined: Wed Apr 18, 2007 9:28 pm
- Location: Glenelg-Marion Area
Re: Glenelg Tram Line Upgrade
DAMN STRAIGHT IT IS!!!!
As if it took them this long to figure that out!!!!
As if it took them this long to figure that out!!!!
Who is online