Page 40 of 54
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Tue Sep 12, 2023 3:50 pm
by Prodical
This project is a bit of a worry. Nothing happening on site and the excavators remain parked. Maybe Multiplex has not taken over the site from the demolition contractor?
The inactivity has gone on for some weeks - puzzling with so many pre-commitments for the hotel + apartments and the market area.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Tue Sep 12, 2023 4:47 pm
by Pikey
I'd suggest it is a contractor handover. I wouldn't be too worried.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Tue Sep 12, 2023 4:49 pm
by AG
Possibly the basement excavation and retaining structures has been contracted out to another civil contractor? Sometimes the basement works and superstructure are done by different contractors on some jobs.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Fri Sep 15, 2023 2:34 pm
by Prodical
No work on the site this week - but I have been looking at this the wrong way.
From the Multiplex signage, it is scheduled to be finished in 149 years
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Fri Sep 15, 2023 7:29 pm
by timtam20292
I hope work resumes soon.
Sent from my iPhone using Tapatalk
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Sat Sep 16, 2023 2:53 pm
by EBG
Some of the excavators lined up in Gouger st moved today.(Saturday 16/9/2023)
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Wed Sep 27, 2023 11:20 am
by SouthAussie94
Piling here will be starting soon-ish. Not sure on exact timelines but expect this to ramp up in the near future.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Wed Sep 27, 2023 1:19 pm
by timtam20292
Would like to see some action at least before Christmas, so that's good to know.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Wed Oct 04, 2023 2:05 pm
by Smithy84
SouthAussie94 wrote: ↑Wed Sep 27, 2023 11:20 am
Piling here will be starting soon-ish. Not sure on exact timelines but expect this to ramp up in the near future.
By “soon-ish” I assume you mean January?
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Wed Oct 04, 2023 2:52 pm
by rev
Smithy84 wrote: ↑Wed Oct 04, 2023 2:05 pm
SouthAussie94 wrote: ↑Wed Sep 27, 2023 11:20 am
Piling here will be starting soon-ish. Not sure on exact timelines but expect this to ramp up in the near future.
By “soon-ish” I assume you mean January?
Would probably be mid January as there's probably going to be a obligatory Christmas & New Years shut down.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Wed Oct 04, 2023 3:19 pm
by Patrick_27
rev wrote: ↑Wed Oct 04, 2023 2:52 pm
Smithy84 wrote: ↑Wed Oct 04, 2023 2:05 pm
SouthAussie94 wrote: ↑Wed Sep 27, 2023 11:20 am
Piling here will be starting soon-ish. Not sure on exact timelines but expect this to ramp up in the near future.
By “soon-ish” I assume you mean January?
Would probably be mid January as there's probably going to be a obligatory Christmas & New Years shut down.
It's funny the thinking behind the obligatory Christmas / New Year shut down of any works on site that's seen to 'help' trading in the Market precinct during this period, it's inevitably what's delayed this project by a year. I went to the Markets yesterday and it's evident how the mere closure of the arcade and the loss of that section of car parking (sad as that might seem) has obliterated the previous scores of shoppers going through there (no doubt, I'm sure the economy has played its part too) but I don't think shutting down site works over that period will do anything to better or worse the current reality of shopper figures dropping, but rather the sooner they get on with things and have this completed, the better off the Market precinct will be. Maybe a week or two shutdown isn't that much in the scheme of things construction wise, but this whole project has dragged.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Thu Oct 05, 2023 12:26 am
by timtam20292
Tbh, I’m quite annoyed that there is no work occurring here. Delay the demolition by a year, demolition gets underway and is completed only for this to become a quiet site again.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Thu Oct 05, 2023 9:54 am
by Prodical
This project is a real worry - Multiplex are a hi-calibre builder of significant projects. So why these ongoing delays. The apartments sold out pretty quickly over a year ago - and there are supposedly tenants lined up for the hotel and some office space. The new market area would generate income, so what is the problem?
This is reminding me of the EIC building at Lot 14 - lots of initial noise and promises - then nothing.
The difference between this Market project and the construction by Synergy (a local builder) of the Victoria Tower opposite is pretty stark.
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Thu Oct 05, 2023 10:06 am
by timtam20292
My only guess is that the site is so huge that maybe they are waiting to start in the new year.
Sent from my iPhone using Tapatalk
[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels
Posted: Thu Oct 05, 2023 2:23 pm
by rev
I'm sure there's valid reasons why it's taking longer then other developments.